PROJECT UPDATES
Group 41: Franklin Avenue
Franklin Avenue (Leon C. Simon Boulevard - Lakeshore Drive)
Repairs include concrete panel replacements, repairing curbs, installing ADA-compliant accessible ramps and bike lanes. *The scope of work includes sidewalk construction, where none exist.
Apr 29: Permanent striping is underway on Franklin Ave. and is expected to be completed today. Travel lanes are open in both directions.
Mar 25: Franklin Ave. traffic control remains in place as the contractor continues removal and replacement of concrete roadway sections. The Sewerage and Water Board's contractor continues replacement of the existing water main in the south bound lanes. Tie-in of the new water main to the existing water main is expected Monday evening. Once completed, the roadway contractor will switch lanes and begin pavement removal in the left lane heading south bound. Expected completion is the week if April 11. This was extended due to unexpected water and drain pipe construction.
Feb 10: A community informational meeting to discuss the repair of Franklin Avenue from Leon C Simon Drive to Franklin Avenue is scheduled Tuesday, February 16 at UNO Lakefront Arena (south lot entrance) Privateer Room, 6801 Franklin Avenue, New Orleans, LA 70122. The meeting will begin at 6 p.m.
Dec 17: Hard Rock Construction is the apparent low bidder for the project.
Nov 30: The bid letting date has been reset for December 2015. December 9, tentatively.
Oct 19: Construction is anticipated to start in March/April 2016. The bid letting has been rescheduled to take place in November 2015.
Jun 17: DOTD's Paths to Progress Program announces roadway improvements planned for Franklin Avenue, between Leon C. Simon Boulevard and Lakeshore Drive. The bid letting is scheduled for October 2015 with construction anticipated to start in March 2016. A community meeting will be held closer to the start of project.
Group 40: Old Behrman Highway and LB Landry Avenue
Old Behrman Highway (Marr Avenue - LA 428)
L B Landry Avenue (Mardi Gras Boulevard - Jefferson Parish Line)
Repairs include roadway resurfacing, pavement patching, repairing curbs, and installing ADA-compliant accessible ramp. *The scope of work includes sidewalk repairs and the reconfiguration of the Old Behrman Highway, including the removal of a parking to add a two-cycle track and three-foot buffer.
Mar 30: Traffic control is being removed on LB Landry Ave at this time. Both lanes in both directions are open, including bike lanes. The contractor is completing minor punch list items. Please maintain caution.
Mar 25: Behrman Hwy. is open to traffic in both directions, including the newly striped cycle track. The status of minor punch list items remains to be completed.
LB Landry Ave. traffic control will remain in place until next Tuesday to allow the contractor to complete required permanent striping, replace accessible ramps, construct a median accessible ramp at Mardi Gras Blvd., and repair minor punch list items.
Mar 9: Asphalt paving on Behrman Hwy. is complete. Permanent striping continues and the roadway has been reopened to both directions of travel.
Asphalt paving will begin today on LB Landry Ave. and continue through the next several days, weather permitting.
Mar 7: Asphalt paving continues on Behrman Hwy. and should be completed this afternoon, weather permitting. Permanent striping is being laid out today and will continue through this week.
Asphalt paving begins tomorrow on L B Landry Ave. and will continue through this week.
Mar 1: Asphalt paving is underway on Behrman Hwy. and will continue through this week. Travelers are reminded of the one way direction, which remains in affect. Asphalt paving is expected to begin next week.
Feb 19: Cold milling is underway on Behrman Hwy. and will continue through Feb. 23. The milled material is being taken to a designated area in the Skelly Rupp Stadium parking lot where the New Orleans Department of Public Works will begin removing and using it to stabilize shoulders and unpaved roadways in Algiers. Drivers should expect lane shifts as the cold milling continues when the contractor begins milling adjacent lanes to the closed lane. The roadway will remain one way from Marr Ave to LA 428. We appreciate everyone's patience.
Dec 16: Construction expected to begin Monday, January 4. Travel will be limited to one-way traffic on Old Behrman Hwy, between Marr and LA 428, throughout construction. One lane, in each direction, will remain open L B Landry Avenue during the road repairs.
Dec 1: The community informational meeting for the upcoming road repairs to Old Behrman Hwy and L B Landry Avenue took place at 6 p.m. at the William J. Fischer Accelerated Academy. In addition to explaining the road, curb and sidewalk repair, it was announced that the design plans call for Old Behrman Hwy, from Marr Avenue to LA 428, to be reconfigured. The reconfiguration includes eliminating the westbound parking lane and replacing it with a two-way cycle track and three-foot buffer. Travel on Old Behrman Highway will be limited to one-way traffic throughout construction.
Construction is anticipated to begin in January 2016 and reach completion in April 2016. On-street parking during construction working hours, generally 7 a.m. to 5:30 p.m. on Monday through Friday, will not be permissible.
Nov 23: A community informational meeting for Old Behrman Hwy and L B Landry Ave road repairs is scheduled for Tuesday, December 1 at William J. Fischer Accelerated Academy, Cafeteria, 1801 L B Landry Avenue, New Orleans, LA 70114. The meeting is to begin at 6 p.m.
Nov 17: Construction has been rescheduled to start in January 2016 with road repairs reaching completion in April 2016.
Nov 4: Road repairs to Old Behrman Highway (Marr Ave - LA 428) and L B Landry Avenue (Mardi Gras Blvd – Jefferson Parish Line) are expected to start on Tuesday, December 1, 2015 and continue through March 2016. The construction work will include ADA ramp removal and replacement at sidewalk corners, full-depth patching along the corridors, asphalt overlaying and permanent striping.
Oct 19: Hard Rock Construction is the apparent low bidder for the Old Behrman Hwy and L B Landry project with road repairs expected to start in December 2015.
Sept 15: The bid letting for Old Behrman Hwy and L B Landry has been rescheduled for Wednesday, October 14, 2015.
Aug 18: The bid letting for Old Behrman Hwy and L B Landry Ave is scheduled for Wednesday, September 9. Construction is anticipated to begin in December 2015.
June 17: DOTD's Paths to Progress Program announces roadway improvements planned for Old Behrman Highway, between Marr Avenue and Behrman Highway, and L B Landry Avenue, between Mardi Gras Boulevard and the Jefferson Parish Line. The bid letting date is scheduled for September 2015 with construction anticipated to start in December 2015. A community meeting will be held closer to the start of the project.
Group 39: N. Galvez St. and Downman Rd.
North Galvez Street (Orleans Avenue - Elysian Fields Avenue)
Downman Road (Babylon Street - Odin Street)
Repairs include roadway resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Oct 14: Permanent striping is complete on N. Galvez. The striping includes one travel lane, one bike lane and one parking lane.
Oct 7: N. Galvez (Orleans - Elysian Fields): Road repairs are complete, and permanent striping continues. Striping includes one travel lane, one bike lane and one parking lane.
Downman (Babylon - Odin): Road repairs and permanent striping are complete. All travel lanes are open to traffic.
Sept 29: Final walk-through held today. Project has reached substantial completion. Punch-list items, including striping, are underway.
Sept 22: Permanent striping underway at N. Galvez Street as project nears completion.
Sept 18: N. Galvez (Orleans - Elysian Fields): Asphalt paving of the mainline is complete. Crews continue to pave the roadway cross-overs and turn-outs. Striping to follow. One travel lane in each direction remains open to traffic.
Downman (Babylon - Odin): Permanent striping and work list items underway. One travel lane in each direction remains open to traffic.
Sept 10: N. Galvez (Orleans - Elysian Fields): Milling operations continue between A P Tureaud and Elysian Fields. Also, asphalt paving is underway between Orleans and St. Bernard. Intersections within close proximity to the paver will close for 30 to 45 minutes to allow the asphalt to cure and harden. One travel lane in each direction remains open to traffic.
Downman (Babylon - Odin): Asphalt paving is complete. Striping to follow. One lane in each direction remains open to traffic.
Sept 3: Downman (Babylon - Odin): Asphalt leveling and paving underway. Intersections within close proximity to the paving machine will temporarily close for 30 - 45 minutes in addition to the existing alternating lane closures.
N. Galvez (Orleans - Elysian): Milling operations continue. Pavement patching at the A P Tureaud intersection also underway. Paving to follow.
Aug 27: N. Glavez (Orleans - Elysian Fields): Patching is underway at the intersection of A P Tureaud. Milling operations continue, and paving to follow.
Downman (Babylon - Odin): ADA ramps, patching, curb replacement and milling operations are complete. Joint repair underway, and paving operations are scheduled to start next week.
In addition to the existing alternating lane closures, street intersections within close proximity to the paving machine will temporarily close for 30 to 45 minutes during paving operations on the N. Galvez and Downman project segments.
Aug 18: N. Glavez (Orleans - Elysian Fields): Pavement patching and curb and gutter replacement continue. Milling operations to start mid-week. Milling scheduled to start at Orleans and move towards Elysian Fields.
Downman (Babylon - Odin): ADA ramps, patching and milling operations are complete. Median curb placement underway and to continue next week.
Aug 11: N. Glavez (Orleans - Elysian Fields): Installation of ADA ramps complete with the exception of one ramp. Pavement patching, utility adjustments and curb and gutter repairs underway and to continue next week. One travel lane remains open to traffic.
Downman (Babylon - Odin): Pavement patching is near completion, and median curb repair underway. Paving operations to start within two weeks. One lane in each direction remains open for travel.
Aug 4: N. Glavez (Orleans - Elysian Fields): ADA ramp installation and pavement patching continue in the left lane. One travel lane remains open to traffic.
Downman (Babylon - Odin): Pavement patching continues in the median lanes. Curb and gutter repair to begin this week. The outside lanes remain open to traffic.
Jul 28: N. Glavez (Orleans - Elysian Fields): ADA ramp installation and pavement patching underway in the left lane, this week. ADA ramps are complete in the right lane. The right lane remains open to traffic.
Downman (Babylon - Odin): Pavement patching is complete in the right lane, and all ADA ramps have been installed. Crews to swap traffic to the outside lanes this week and start pavement patching in the median lanes.
Jul 15: N. Glavez (Orleans - Elysian Fields): ADA ramp installation and pavement patching continue in the right lane. Patching and ADA ramp installment of the left lane to follow. One lane remains open to traffic.
Downman (Babylon - Odin): ADA ramp installation and milling operations are complete. Patching and median curb repair underway. One lane remains open to traffic.
Jul 1: Downman (Babylon – Odin): Cold milling operations are complete. Pavement patching underway and will continue next week. N. Galvez (Orleans – Elysian Fields): ADA ramp removal and replacement underway and to continue for the next three weeks.
Jun 23: Downman (Babylon - Odin): ADA ramp removal and replacement underway and cold milling operations to follow.
Jun 16: Paths to Progress will start the Downman Road (Babylon – Odin) and N. Galvez (Orleans – Elysian Fields) project on Monday, June 23. Crews will begin with pavement excavation and ADA ramp removal and replacement on Downman Road. Road repairs of N. Galvez Street will begin two weeks from the start date. One lane will remain open to traffic throughout construction.
Repairs include roadway resurfacing, pavement patching, repairing curbs and installing ADA-compliant accessible ramps. Also, a dedicated bike lane will be installed on N. Galvez Street between Orleans and Elysian Fields. Crews may begin tree trimming and installing curb inlet protection in preparation of the project this week. Project anticipated to reach completion late August 2014. All dates are dependent on weather and other unforeseen events.
Jun 3: Road repairs scheduled to start later this month and last approximately two months.
May 6: Community held tonight at the New Life Church of Christ Holiness USA, specifically for the Downman Road upcoming repairs.
April 29: A community will be held Tuesday, May 6 at 6 pm at the New Life Church of Christ Holiness USA, 5918 Babylon Street, New Orleans, LA 70126 to discuss upcoming road repairs to Downman Rd. Please access the church parking lot from the main entrance on Babylon Street.
April 22: Paths to Progress hosts a community meeting tonight, April 22 at 6pm at the St. Ann Activity Center, 2117 Ursulines Avenue, New Orleans, LA 70116 to discuss upcoming road repairs. On-street parking available along Ursulines Ave and neighboring streets.
April 15: A community meeting will be held Tuesday, April 22 at 6pm at the St. Ann Activity Center, 2117 Ursulines Avenue, New Orleans, LA 70116 to discuss upcoming road repairs. Since St. Ann Activity Center does not have a designated parking area, on-street parking is available along Ursulines Avenue and neighboring streets.
Group 38: MacArthur Blvd. and Sullen Pl.
MacArthur Boulevard (General DeGaulle Drive - Kabel Drive)
Sullen Place (General DeGaulle Drive - Patterson Drive)
Repairs include roadway resurfacing, pavement patching, curb repair, installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
June 7: Punch-list items are complete. All road repairs are complete.
June 2: The permanent striping for MacArthur Blvd and Sullen Place is complete. All lanes are open to traffic for each roadway. Only punch-list items remain as a final walk-through was held on Friday, May 29.
May 29: Two-way traffic is now permissible on Sullen Place: With permanent striping nearing completion, Sullen Place has re-opened to traffic in both directions.
May 26: Permanent striping on MacArthur Boulevard nears completion: Crews to stripe the remaining corner zones tomorrow, May 27. Roadway is completely open to traffic.
May 18: The striping layout on MacArthur Blvd and Sullen Place is near completion. Crews are to begin permanent striping on Thursday, May 21 pending weather and other unforeseen events.
May 11: Striping of MacArthur Blvd to include a dedicated bike lane: Crews are currently laying out the striping for MacArthur Blvd between General DeGaulle and Kabel. Striping plans include two travel lanes, one bike lane and one parking lane on each side of the roadway.
May 4: Crews have completed paving operations on Sullen Place. Minor work list items underway. The striping layout is to start within a week or two.
April 29: MacArthur Blvd (General DeGaulle - Kabel): ADA ramp installation, curb and gutter repairs, pavement patching and paving operations are complete. Traffic loop repairs underway and striping to follow.
Sullen Place (General DeGaulle -Patterson): Paving operations underway. Paving of the mainline is complete while crews continue to overlay the parking lanes. One-way northbound traffic continues to be implemented.
April 17: It's been a week of bad weather conditions; construction activity is scheduled to resume on Monday, April 20. Crews will work on traffic loops on MacArthur Boulevard and asphalt wearing on Sullen Place.
April 7: The paving of turn-outs and crossovers is underway on MacArthur Blvd. Asphalt leveling on Sullen Place is scheduled to start this week.
March 30: Asphalt paving operations resume on MacArthur Blvd between General DeGaulle and Kabel. Crews will begin paving on Sullen Place this week or next.
March 26: Construction activities are canceled for the day due to rain. Milling and paving operations will resume on MacArthur and Sullen Place when weather permits.
March 24: Asphalt leveling and paving underway on MacArthur between General DeGaulle and Kabel. In addition to the ongoing one-lane closures, intersections are restricted for 30 to 45 minutes at a time to allow the newly laid asphalt to harden and cure.
Milling operations underway on Sullen Place between Patterson and General DeGaulle. Paving to follow. One-way northbound traffic continues throughout construction.
March 20: Crews are milling the turnouts of Sullen Place. One-way northbound traffic is being implemented from Patterson to General DeGaulle. Asphalt leveling and paving to begin on MacArthur between General DeGaulle and Kabel on Monday, March 23. In addition to the ongoing one-lane closures, intersections will close for 30 to 45 minutes at a time to allow the newly laid asphalt to harden and cure.
March 17: Pavement patching and curb and gutter repair continue on Sullen Place. Milling operations to start next week.
March 16: Milling operations underway on MacArthur Blvd from General DeGaulle to Kabel. One lane in each direction remains open to traffic. Paving to start next week, weather permitting.
March 9: Planned milling operations for MacArthur rescheduled to due to rain. Road repairs to resume when weather permits.
Feb 27: Pavement patching, curb repair and ADA ramp removal and replacement continue on MacArthur and Sullen Place. Cold milling operations to follow.
Feb 16: MacArthur Blvd (General DeGaulle - Kabel): Pavement patching underway in the median lanes and to continue throughout the week.
Sullen Place (General DeGaulle -Patterson): One-way northbound traffic continues throughout construction. Work at the General Meyer and Sullen intersection is underway. ADA ramp installation and pavement patching continue this week.
Feb 13: Paths to Progress construction work will be reduced or restricted on MacArthur Blvd on Saturday, February 14 so that parking is available for those attending the Algiers parade. Road repairs of Sullen Place between General DeGaulle and Patterson will continue throughout the weekend.
Feb 9: MacArthur Blvd (General DeGaulle - Kabel): Pavement patching is planned to start today, Feb. 9, in the median lanes. Curb repair and patching of the outside lanes are complete. Work in the median lanes will continue next week.
Sullen Place (General DeGaulle - Patterson): One-way northbound traffic continues throughout construction. More than 50% of the ADA ramps have been installed. ADA ramp installation and pavement patching will continue this week. Work at the General Meyer and Sullen intersection is planned to start within the upcoming weeks.
Jan 27: The New Orleans Regional Transit Authority announces detours from Sullen Place in Algiers. Due to the Department of Transportation and Development's Paths to Progress road rehabilitation project on Sullen Place, the RTA has established detours on Sullen Place going to Canal Street (inbound direction) are in effect until April 2015. Buses will detour going to Canal Street from Bennett Street and Berkley Drive via General Meyer Avenue and Woodland Drive.
Inbound Stops on Sullen Drive between General De Gaulle Drive and General Meyer Avenue are suspended until the State of Louisiana‘s road project on Sullen Place is completed. These bus stops are:
Stop ID: 2615 Berkley at Kent
Stop ID: 2616 Berkley at Dickens
Stop ID: 2617 Berkley at Sullen
Stop ID: 2618 Sullen at Fairfax
Stop ID: 2619 Sullen at Maumus
Stop ID: 2620 Sullen at Stratford
Stop ID: 2621 Sullen at Southwood Apts.
Passengers should catch buses on outbound stops going to Bennett Street and Berkley Drive to travel to Canal Street.
Help for People with Disabilities: Assistive services or copies of public documents can be provided in an alternate format. Please call (504) 248-3900 or (504) 827-7833 (for persons with a hearing impairment).
Jan 26: MacArthur Blvd (General DeGaulle - Kabel): Crews continue ADA ramp removal and replacement, pavement patching and curb and gutter repairs in the high lanes from DeGaulle to Holiday. Road repairs continue in the low lane of MacArthur between Holiday and Kabel.
Sullen Place (General DeGaulle -Patterson): One-way northbound traffic is being implemented throughout construction. The installation of bus pads and ADA ramps are underway as crews continue panel replacements.
Jan 14: MacArthur Blvd (General DeGaulle - Kabel): ADA ramp removal and replacement underway between DeGaulle and Holiday. Tree trimming also underway in the median.
Sullen Place (General DeGaulle -Patterson): One-way northbound traffic is being implemented throughout construction. ADA ramp removal and replacement underway in the parking lanes. Pavement patching continues in the southbound traveling lane.
Jan 12: Construction underway on MacArthur Boulevard and Sullen Place.
Jan 7: The construction of MacArthur Boulevard (General DeGaulle Drive - Kabel Drive) and Sullen Place (General DeGaulle Drive - Patterson Drive) is scheduled to start on Monday, January 12 and reach completion by April 2015.
The southbound traffic of Sullen Place will close for the duration of the project. Only one-way northbound traffic will be permitted on Sullen Place, between General DeGaulle and Patterson. Travelers are encouraged to use an alternative route such as Woodland Highway.
One lane in each direction of MacArthur will remain open to traffic throughout construction.
Jan 5: Road repairs scheduled to start on Monday, Jan 12. Temporary lane closures and restricted parking will be implemented throughout construction.
Dec 16: Community informational meeting held at the Algiers Regional Library to discuss upcoming road repairs to MacArthur Boulevard and Sullen Place.
Dec 9: A community informational meeting will be held Tuesday, December 16 at 6 p.m. at the Algiers Regional Library, 3014 Holiday Drive, New Orleans, LA, 70131 to discuss upcoming roadway repairs.
Group 37: Newton St. and General DeGaulle Dr.
Newton Street (Whitney Avenue - Behrman Avenue)
General DeGaulle Drive (Holiday Drive - Woodland Drive)
Repairs include pavement removal and replacement, curb repair if needed, and installing ADA-compliant accessible ramps. *Improvements to Newton Street will also include driveway and sidewalk repairs and landscaping. Street light installation may be included in the project, pending construction cost and feasibility.
Dec 2: Ribbon-cutting ceremony to be held on Thursday, December 4 at 11 a.m. at the Craige Cultural Center, 1800 Newton Street, New Orleans, LA 70114.
Nov 24: Final walk through of project held today. All lanes have reopened on Newton Street and General DeGaulle Drive as crews complete punch list items and clean construction site.
Nov 19: Tree planting and permanent striping of Newton Street underway.
Nov 17: Permanent striping of General deGaulle Drive between Holiday and Woodland is complete. All lanes have reopened to traffic.
Nov 14: Today, crews continued concrete pours and street light installations and began tree planting on Newton between Whitney and Behrman. Permanent striping on General deGaulle between Holiday and Woodland will continue next week
Nov 6: Newton (Whitney – Behrman): Pavement patching is complete. Pedestrian street light installments are underway and to continue next week. Landscaping and striping to follow. One lane in each direction remains open to traffic.
General deGaulle (Holiday – Woodland): Pavement patching is complete. Sidewalk and ADA ramp installations continue westbound. Permanent striping underway. All eastbound lanes are open to traffic. Only one westbound travel lane remains open to traffic.
Oct 27: Newton (Whitney – Berhman): Westbound lane remains closed to traffic through Friday, October 31. Traffic is only one-way eastbound as crews continue concrete panel replacements. Pedestrian street light installments to begin within two weeks.
General deGaulle (Holiday – Woodland): Eastbound lanes are open to traffic. Pavement patching and ADA ramp installments continue westbound. Only travel lane is open westbound.
Oct 21: Newton (Whitney - Berhman): Closure of westbound traffic scheduled for Wednesday, October 21 through Friday, October 31. During this time, Newton will only have one-way eastbound traffic. This work is necessary to facilitate ongoing roadway repairs. The westbound lane of Newton Street, between Whitney Avenue and Behrman Avenue, will temporarily close. Traffic in the westbound direction will be detoured using Mardi Gras Boulevard.
Oct 15: Newton (Whitney – Berhman): ADA ramp installation and sidewalk repairs are complete. Patching is underway in the travel lanes and will continue next week. One travel lane in each direction remains open.
General deGaulle (Holiday – Woodland): Pavement patching and ADA ramp removal and replacement are underway and will continue next week. One travel lane in each direction remains open.
Oct 1: Newton (Whitney – Berhman): ADA ramp installation and sidewalk repairs are underway. Patching is complete in the parking lanes and will continue in the travel lanes, next week. One travel lane in each direction remains open.
General deGaulle (Holiday – Woodland): Crews continue patching in the median lanes. Patching is complete in the outside lanes. One travel lane in each direction remains open.
Sept 23: Newton (Whitney – Berhman): ADA ramp installment, concrete panel replacements, patching, sidewalk repairs and driveway adjustments continue this week. One travel lane in each direction remains open to traffic.
General deGaulle (Holiday – Woodland): Concrete panel replacements, patching and sidewalk repairs are underway and will continue next week. One travel lane in each direction remains open to traffic.
Sept 19: Newton (Whitney - Berhman): Sidewalk and driveway installments in southside lanes underway and to continue next week. One travel lane remains open in each direction.
General deGaulle (Holiday - Woodland): Concrete panel replacements underway and to continue next week. One travel lane remains open in each direction.
Sept 12: Newton (Whitney – Berhman): Patching in the parking lane is complete. Removal and replacement of sidewalks and specific driveway locations underway on the left roadway. One travel lane in each direction remains open to traffic.
General deGaulle (Holiday – Woodland): Patching underway at the Huntlee crossover and in the left lane/left roadway between Woodland and Huntlee. Concrete has been placed for the Kabel and Lennox sidewalks. Sidewalk repairs, patching and catch basin adjustments on the left and right roadway will continue next week. One travel lane in each direction remains open to traffic.
Sept 4: Newton (Whitney - Behrman): ADA ramp installation and pavement patching continue. One lane in each direction remains open to traffic.
General deGaulle (Holiday - Woodland): Pavement patching and ADA ramp removal and replacement continue. Sidewalk repairs at the intersection of Kabel Drive near completion. One lane in each direction remains open to traffic.
Aug 29: Newton (Whitney - Behrman): ADA ramp installation and pavement patching underway and to continue next week. One lane in each direction remains open to traffic.
General deGaulle (Holiday - Woodland): ADA ramp removal and replacement and pavement patching underway. Sidewalk repairs at the intersection of Kabel Drive continue. One lane in each direction remains open to traffic.
Aug 18: Road repairs start today. This week, traffic control installment, tree-trimming, sawcutting and ADA ramp removal and replacement are underway for both street segments.
Aug 11: Construction work and lane closures to start on Monday, August 18. Contractor is delivering community notices today.
Aug 7: Construction crews will begin road repairs on Newton Street, between Whitney Avenue and Behrman Avenue, and General DeGaulle Drive, between Holiday Drive and Woodland Drive, on Monday, August 18. The road repairs are valued at approximately $3 million and will include concrete panel removal and replacement, curb repair and ADA-compliant ramp installments.
Betterments for Newton Street also include landscaping/tree installments and sidewalk adjustments. Negotiations continue with the contractor to install pedestrian street lights along the street segment.
This project is expected to last 2 to 3 months.
All dates and planned construction activities are subject to change pending weather and other unforeseen events.
Jul 23: Community meeting held today, at 6 p.m. at the Algiers Regional Library to discuss the upcoming roadway repairs.
Jul 11: A community meeting will be held on Wednesday, July 23 at 6 p.m. at the Algiers Regional Library, 3014 Holiday Drive, New Orleans, LA 70131 to discuss upcoming road repairs.
Group 36: Newton St., Pace St., Mercedes Blvd.
Newton Street (Teche Street - L B Landry Avenue/Whitney Avenue)
Pace Boulevard (Wall Boulevard - General Meyer Avenue)
Mercedes Boulevard (MacArthur Boulevard - Hershel Street)
Repairs include roadway resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Jun 19: Crews have reached substantial completion of this project. Resurfacing and striping is complete, with minor work items to be performed. All street segments are open for travel.
Jun 3: Newton (Teche - L B Landry/Whitney): Paving operations continue this week. Striping layout and permanent striping to follow. Pace (Wall – General Meyer): Asphalt paving is complete. Permanent striping underway.
Mercedes (MacArthur – Herschel): ADA ramp installation, asphalt resurfacing and striping are complete.
May 28: Newton (Teche - L B Landry/Whitney): Paving operations to start next week. During the asphalt paving operations, there will be rolling closures of street intersections, lasting 30 - 45 minutes at a time, in addition to the established lane-closures.
Pace (Wall – General Meyer): Paving operations of the mainline and cross-overs are complete. Crews to continue paving the street turn-outs. Permanent striping to follow. One lane remains open to traffic.
Mercedes (MacArthur – Herschel): ADA ramp installation, asphalt resurfacing and striping are complete.
May 19: Newton (Teche - L B Landry/Whitney): Asphalt leveling is underway. Paving operations to follow. Eastbound traffic is detoured to Opelousas Avenue. Mercedes (MacArthur – Herschel): Paving operations are underway this week. One lane remains open to traffic.
Pace (Wall – General Meyer): Asphalt leveling is underway. Paving operations to follow. Paving will be a moving operation; therefore, roadway intersections within close proximity to the paver will be temporarily closed for 30-45 minutes at a time in addition to the one-lane closure already established.
May 7: Newton (Teche - L B Landry/Whitney): Milling operations are complete. Pavement patching continues. Eastbound traffic is detoured to Opelousas Avenue for the remainder of construction.
Pace (Wall – General Meyer): ADA ramp installation is complete. Pavement patching is underway and to continue next week. One lane remains open to traffic. Mercedes (MacArthur – Herschel): ADA ramp installation is complete. Pavement patching underway. One lane remains open to traffic.
April 28: A detour is planned for Newton Street eastbound lanes, starting Tuesday, April 29. Traffic will be detoured to Opelousas Avenue. Detour will facilitate cold milling, patchwork and paving operations. Milling operations start tomorrow on Newton. The eastbound detour is expected to last 4-6 weeks.
Concrete patchwork and structure adjustments underway and to continue next week on Mercedes Blvd. ADA ramp installation and pavement patching underway and to continue next week on Pace Blvd.
April 18: Newton (Teche - L B Landry/Whitney): ADA ramp removal and replacement to continue next week along with curb and gutter repairs. Milling operations to follow. Pace (Wall – General Meyer) Milling operations are complete. ADA ramp removal and replacement to continue next week. Pavement patchwork to start next week. Mercedes (MacArthur – Herschel): One-lane closures will be implemented, starting on Monday, April 21. Crews to begin saw-cutting joints and ADA removal and replacement, next week.
April 7: Construction of Newton Street and Pace Boulevard roadway segments to start tomorrow. Crews will begin with milling operations on Pace and ADA removal and replacement on Newton. One-lane closures will be implemented throughout construction. Project to reach completion June 2014.
April 1: Road repairs of Newton and Pace street segments to start next Tuesday, April 8. Repairs of Mercedes Blvd are scheduled to start April 21, after LEAP testing is complete at Habans Charter School. Construction expected to last 8-10 weeks. Alternating lane closures will be implemented but one lane of travel will remain open.
Mar 25: Road repairs are scheduled to start Tuesday, April 8. Alternating lane closures will be implemented, but one lane of travel will remain open to traffic. On-street parking will be restricted during construction working hours. Standard working hours are 7 a.m. to 5:30 p.m. on Monday through Friday. Crews may work weekends, holidays or extend working if the City of New Orleans grants permission.
Mar 6: Construction to begin after Tuesday, March 25.
Feb 25: Community meeting held at 6pm at the Delgado Community College, West Bank Campus, LaRocca Hall, Room 142, 2600 General Meyer Avenue, New Orleans, LA 70114 to discuss road repairs scheduled to start next month.
Feb 18: A community meeting will be held Tuesday, Feb 25 at 6pm at the Delagado Community College, West Bank Campus, Larocca Hall, Room 142, 2600 General Meyer Avenue, New Orleans, LA 70114 to discuss upcoming road repairs. Free parking is available on campus.
Group 35: Baronne, Burgundy and S. Peters Streets
Baronne Street (Canal Street - Calliope Street)
Burgundy Street (Esplanade Avenue - Elysian Fields Avenue)
S. Peters Street (Canal Street - Calliope Street)
Repairs include roadway resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. Shared bike lanes will also be installed on the street segments. *The scope of includes sidewalk repairs.
Nov 19: The reconfiguration of Baronne Street has been rescheduled to start tomorrow, November 20. Baronne will be reconfigured to remove on travel lane from Canal Street to Calliope Street and replace it with a dedicated bike lane.
Nov 1: Reconfiguration of Baronne Street has been postponed until futher notice per the direction of the City of New Orleans.
Oct 29: Baronne Street will be reconfigured to include one bike lane. In conjunction with the City of New Orleans Department of Public Works, the Louisiana Department of Transportation and Development’s Paths to Progress will re-configure Baronne Street to remove one travel lane from Canal Street to Calliope Street and replace it with a dedicated bicycle lane. The installation of a bike lane on Baronne Street is consistent with the City’s Master Plan and the Complete Streets Program. The striping of the bike lane will take place from Saturday, November 1 through Sunday, November 2.
Construction of the $2.9 million Baronne project began on March 24. The City has funded 20 percent of the project, with the Regional Planning Commission matching 80 percent. The patching, resurfacing, removing and replacing of sidewalk segments and installing of ADA ramps are complete. Configuring the bike lane will be the last stage of the project.
Oct 16: The left lane of S. Peters Street, between Julia and Notre Dame, will temporarily close to traffic from Thursday, Oct. 16 to Monday, Oct. 20 as crews complete corrective work. One lane will remain open to traffic throughout the repairs.
Oct 9: Sidewalk removal and replacement on Baronne Street between Lafayette and Howard nears completion. All travel lanes and sidewalk areas are open. Next week, crews plan to complete minor details such as sealing joints and coring termite traps.
Oct 2: Baronne (Calliope - Canal): Crews continue sidewalk removal and replacement on Baronne, between Lafayette and Julia. Work to continue for the next two to three weeks. One travel lane remains open to traffic
Sept 24: Baronne (Calliope - Canal): Sidewalk removal and replacement continue at the 600 and 700 blocks of Baronne, between Lafayette and Julia. A one-lane closure is in place from Lafayette to Howard; one travel lane remains open to traffic.
Sept 19: Sidewalk removal and replacement continues on Baronne between Girod and Julia. Crews plan to start sidewalk repairs at the 600 block, between Lafayette and Girod, on Wednesday, September 24. Repairs between Julia and Howard are substantially complete. One travel lane remains open to traffic
Sept 9: Sidewalk repairs underway on Baronne between Girod and Howard. Construction from Girod to Julia will continue throughout the month of September. Repairs between Julia and Howard are nearing completion. One travel lane remains open to traffic. On-street parking is limited.
Aug 29: Sidewalk repairs at the 700 block of Baronne, between Girod and Julia, is scheduled to start Tuesday, Sept 2. Repairs between Julia and Howard are near completion.
Aug 11: South Peters (Calliope - Canal): Paving and permanent striping complete. Work list items underway. One lane remains open to traffic.
Baronne (Canal - Calliope): Paving operations complete with the exception of the parking lane at the 500 block. Striping underway, and crews to begin sidewalk removal and replacement at the 800 block, between Julia Street and Howard Avenue, this week. One travel lane remains open to traffic.
Burgundy (Esplanade - Elysian Fields): Striping complete. Work list items continue between Touro Street and Pauger Street. One lane remains open for travel.
Aug 7: Baronne (Canal - Calliope): Asphalt paving operations continue at the Baronne and Poydras intersection and between Canal and Common. Also, crews will start paving between Common and Gravier today, August 7. The New Orleans Police Department is on-site to assist with traffic management. The Common Street and Gravier Street intersections will remain open to traffic, while the travel lanes and parking lanes are closed to faciliate paving operations.
Aug 4: To facilitate paving operations, the temporary alternating closures of the Baronne and Poydras intersection will continue tomorrow, August 5 from 6:30 a.m. to 2 p.m. Paving operations of the eastbound lanes are complete, and crews will continue paving the remaining westbound lanes. The left turn from Poydras Street and the outside travel lanes (closet to median) will remain open to traffic.
Also, the New Orleans Police Department will assist with traffic management, and access to businesses and parking garages within the project limits will be permitted.
July 31: Baronne/Poydras Intersection will have temporary alternating lane closures between Saturday, August 2 at 6:45 a.m. to Sunday, August 3 at 7 p.m. The temporary closures will facilitate asphalt paving operations.
July 31: South Peters (Canal - Calliope): Striping and minor work list items underway. One lane remains open to traffic.
Baronne (Canal - Calliope): Asphalt paving operations continue. Paving of turn-outs and the Howard, Lafayette and Union intersections are underway. Paving of the Poydras intersection to follow. Then, crews will return to the 100 and 200 blocks to lay asphalt. One travel lane remains open to traffic while intersections within close proximity to the paver will remain closed until the asphalt cools and hardens.
Burgundy (Esplanade - Elysian Fields): Minor work list items, striping and installment of bike symbols are underway. One lane remains open for travel.
Jul 22: South Peters (Canal - Calliope): Paving of turn-outs continues this week. Striping to follow.
Baronne (Canal - Calliope): Asphalt paving operations underway. One lane remains open to traffic for travel.
Jul 15: South Peters (Canal - Calliope): Paving of travel and parking lanes is complete. Paving of turn-outs underway. Striping to follow.
Baronne (Canal - Calliope): Paving operations to start tomorrow, July 16, weather permitting. Paving schedule has been adjusted to start at Union street and move towards Howard. Then, crews will continue paving from Howard to Calliope. The 100 and 200 blocks of Baronne will be paved last.
Burgundy (Esplanade - Elysian Fields): Minor work list items continue. Striping to follow.
Jul 9: South Peters (Canal - Calliope): Paving operations underway in the parking lane and Poydras intersection. Paving from Poydras to Canal to follow. One lane remains open to traffic.
Baronne (Canal - Calliope): Leveling operations continue near Calliope. Leveling of the 100 and 200 blocks (Canal - Union) to follow. The leveling of the two blocks will require complete closure to through traffic. The closure will only be during construction working hours. Also, paving operations to start next week. Paving will start at Union and move towards Howard. One lane will remain open to traffic during paving operations.
Burgundy (Esplanade - Elysian Fields): Minor work list items continue. Striping to follow.
Jun 27: Baronne (Canal - Calliope): Leveling will continue this weekend between Union and Howard. Crews will return to the 100 and 200 blocks of Baronne early next week for leveling operations. The leveling of the two blocks will require complete closure to through traffic. The closure will only be during construction working hours. Once leveling is complete, paving will begin.
Burgundy (Esplanade - Elysian Fields): Crews continue work-list items. All lanes are open for travel.
S. Peters (Canal - Calliope): Asphalt paving and utility adjustments of the mainline continue. Paving of the turn-outs and cross-overs to follow. One lane remains open to traffic.
Due to the discovery of utility failures and associated pavement failure, time extension has been granted. Anticipated completion date is late July 2014.
Jun 25: Baronne (Canal - Calliope): Asphalt leveling to start today, June 25 at Union and move towards Poydras. Once all asphalt leveling from Union to Calliope is complete, crews will return to the 100 and 200 blocks of Baronne. The leveling of the two blocks will require complete closure to through traffic. The closure will only be during construction working hours.
June 19: Asphalt paving operations of South Peters Street between Calliope and Canal are underway and will continue next week. One lane remains open to traffic.
June 12: Baronne (Canal - Calliope): Closure of the 100 and 200 blocks is rescheduled to start today at 2 p.m. and re-open by Sunday, June 15. Pavement patching and ADA ramp installations underway between Gravier and Calliope, and to continue next week.
South Peters (Canal - Calliope): Pavement patching continues near the Harrah’s location. Asphalt paving to start next week. Paving is a moving operation. Street intersections within close proximity to the paver will be temporarily closed for 30 – 45 minutes at a time, in addition to lane-closures already in place.
Burgundy (Esplanade - Elysian Fields): Paving operations are complete. Minor work list items underway. All lanes are open to traffic.
Jun 11: Temporary two-block closure of Baronne Street, between Gravier Street and Canal Street, will be implemented from Friday, June 13 at 2 p.m. to Monday, June 16 at 10 a.m. The temporary closure of the 100 and 200 blocks will facilitate cold milling operations. The Common Street and Gravier Street intersections will remain open to traffic and only close intermittently for 30 to 45 minutes. Access to the businesses and parking garages within the project limits will be allowed.
May 29: Burgundy (Esplanade - Elysian Fields): Paving operations to be complete by Monday, June 2. Crews to begin the layout of striping, street tile replacements and minor work items next week. One lane remains open to traffic.
South Peters (Canal - Calliope): Pavement patching and ADA ramp installation continue. Asphalt paving to start mid-next week. Paving is a moving operation. Street intersections within close proximity to the paver will be temporarily closed for 30 – 45 minutes at a time, in addition to lane-closures already in place.
Baronne (Gravier - Calliope): Milling operations are soon complete. ADA ramp installation and pavement patching underway and to continue next week. Asphalt paving operations to start in approximately two weeks. One lane remains open to traffic.
May 20: Burgundy (Esplanade - Elysian Fields): Paving operations continue tomorrow, May 21. Paving will require temporary road closures. Please use alternative routes, including St. Claude Avenue and Royal Street.
S. Peters (Canal - Calliope): Pavement removal and repair underway. Concrete placement scheduled for Thursday, May 22. Crews also continue ADA ramp installations between Calliope and Poydras.
Baronne (Gravier - Calliope): Milling operations continue this week between Poydras and Howard. ADA ramp removal and replacement also underway.
May 15: South Peters (Canal – Calliope): Pavement patching underway and to continue next week. There will be no left turn permitted from Poydras onto S. Peters while the pavement patch located at S. Peters and Poydras is under construction.
Burgundy (Esplanade – Elysian Fields): Pavement patching and ADA ramp installations are complete. Asphalt paving operations to start tomorrow, May 16. Burgundy Street between Esplanade and Elysian Fields will be closed for three – five days during the paving operations. For the temporary closure, please use alternative routes including St. Claude Avenue and Royal Street.
Baronne (Gravier – Calliope): Milling operations to start tomorrow, May 16. ADA ramp installation underway and will continue next week. The starting point of the project has changed from Canal to Gravier to facilitate the undergoing apartment complex renovations at the 100 and 200 blocks of Baronne Street. Repairs will be made to the two-blocks after the apartment construction is complete. One-lane remains open for travel.
May 13: Temporary closure of Burgundy Street (Esplanade - Elysian Fields) scheduled to start Thursday, May 15 and last three to five days. The temporary closure is to facilitate paving operations; please use alternative routes, including St. Claude Avenue and Royal Street.
May 8: South Peters (Canal – Calliope): Milling operations are near completion. ADA ramp installation and pavement patching are underway and will continue next week. One lane remains open for travel.
Burgundy (Esplanade – Elysian Fields): Drainage pipeline removal and replacement at the intersection of Burgundy and Frenchmen is complete. Paving operations to start on Wednesday, May 14. The established one-lane closure will be adjusted to facilitate the asphalt overlay.
Baronne (Canal – Calliope): ADA ramp removal and replacement rescheduled to start on Monday, May 12. One-lane closures will be implemented throughout construction. The starting point of the project has changed from Canal to Gravier to facilitate the undergoing apartment complex renovations at the 100 and 200 blocks of Baronne Street. Repairs will be made to the two-blocks after the apartment construction is complete.
May 1: South Peters (Canal – Calliope): Milling operations from Calliope to Poydras are underway. Crews to start milling between Poydras and Canal next week. One lane remains open for travel.
Burgundy (Esplanade – Elysian Fields): Pavement patching underway, and the drainage pipeline removal and replacement continues at the intersection of Burgundy and Frenchmen. One lane of travel remains open to traffic with intermittent road closures at the Frenchmen/Burgundy intersection to allow the loading of construction trucks. Crews plan to begin paving operations of Burgundy next week. Paving is a moving operation; therefore, intersections within close proximity to the paving machine will be temporarily restricted for 30-45 minutes in addition to the alternating one-lane closures already in place.
Baronne (Canal – Calliope): ADA ramp removal and replacement to start on Monday, May 5. One-lane closures will be implemented throughout construction. The starting point of the project has changed from Canal to Gravier to facilitate the undergoing apartment complex renovations at the 100 and 200 blocks of Baronne Street. Repairs will be made to the two-blocks after the apartment construction is complete.
April 22: South Peters (Canal – Calliope): Milling operations from Calliope to Poydras will start tomorrow. ADA ramp installation underway and to continue next week. One lane remains open for travel. Burgundy (Esplanade – Elysian Fields): Crews to complete milling operations this week. Drainage pipeline removal and replacement is underway at the intersection of Burgundy and Frenchmen. There may be intermittent road closures at the intersection to allow loading of construction trucks.
Baronne (Canal – Calliope): Crews plan to start road repairs of Baronne Street the week of May 5. One-lane closures will be implemented throughout construction.
April 14: Crews have adjusted the schedule to perform cold milling operations on Burgundy Street before milling South Peters Street. The cold milling of Burgundy between Esplanade and Elysian Fields is planned to start tomorrow, April 15, weather pending. Pavement patching on Burgundy will immediately follow the completion of milling. Milling operations of South Peters between Canal and Calliope are scheduled to start the week of April 21.
April 10: S. Peters (Canal – Calliope): ADA ramp installation continues on the left side (riverside) of the roadway. Next week, crews to begin milling operations from Calliope to Poydras. Burgundy (Esplanade – Elysian Fields): Crews to complete ADA ramp installation on the left side (riverside) of the roadway by Friday, April 11. Milling operations to start the week of April 21 or sooner.
Baronne (Canal – Calliope): ADA ramp removal and replacement between Gravier and Calliope to start on Monday, April 21. The starting point of the project has changed from Canal to Gravier to facilitate the undergoing apartment complex renovations at the 100 and 200 blocks of Baronne Street. The City will repair the two-blocks after construction of the apartment complex is complete. All lanes of Baronne are currently open for travel. One-lane closures will be implemented starting April 21.
April 7: Patchwork continues in the lakeside lane of S. Peters Street. Crews to begin pavement removal in the riverside lane on Thursday, April 10. ADA ramp removal and full depth patchwork underway in the riverside lane of Burgundy. Milling operations of Burgundy to start next week.
April 1: Pavement removal and full depth patchwork continue in the lakeside lane of Burgundy and S. Peters street segments. Construction activities and lane closures of Baronne Street are scheduled to start April 21.
Mar 24: Road repairs began today. Excavation underway at sidewalk corners of Burgundy Street for the installation of ADA ramps. Crews are also excavating areas where patching is needed on S. Peters between Canal and Calliope. Cold milling operations will also start this week. On-street parking during construction working hours will be restricted. Standard working hours are Monday - Friday from 7 a.m. to 5:30 p.m. Crews may work weekends, holidays or extend working hours if granted permission.
Mar 11: Road construction and lane closures to start Monday, March 24.
Mar 5: Construction to start after Friday, March 14.
Feb 20: Community meeting to be held tonight at 6pm at the World War II Museum, Louisiana Memorial Pavilion, 945 Magazine Street, New Orleans, LA 70130 to discuss upcoming road repairs planned to start next month.
Feb 13: A community meeting will be held Thursday, Feb 20 at 6pm at the World War II Museum, Louisiana Memorial Pavilion, 945 Magazine Street, New Orleans, LA 70130 to discuss upcoming road repairs.
Group 34: Congress Dr.
Congress Drive (Chef Menteur Highway – Hayne Boulevard)
Repairs include concrete reconstruction, resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. Bus pad improvements and a designated bikeway will also be provided throughout the corridor. Congress from Prentiss to Hayne will include concrete reconstruction rather than the asphalt overlay. *The scope of work does not include sidewalk or driveway repairs.
Jul 15: Permanent striping of Congress Drive is complete. All lanes are open for travel.
Jun 25: Construction between Prentiss and Hayne is on-going. The traffic control devices (traffic signage, barricades, cones, inlet curb protection, etc.) will remain in place while crews determine corrective action to improve durability and to meet state specifications. Crews will return to the project site to perform improvements and complete striping.
May 23: Permanent striping is complete between Chef Menteur and Prentiss. Striping between Prentiss and Hayne to follow.
May 9: Striping layout is complete between Chef Menteur and Prentiss. Crews to start permanent striping next week.
May 2: Paving operations are complete. Next week, crews will begin permanent striping and continue cleanup efforts and minor work items.
April 21: Paving operations continue this week. Asphalt paving is underway in the parking lane and turn-outs between Prentiss and Chef Menteur. Striping to follow.
April 14: Asphalt paving operations, between Chef Menteur and Prentiss, begin today. Crews plan to continue the asphalt overlay next week.
April 4: Congress (Chef Menteur - Prentiss): Utility adjustments to continue next week. Paving to start immediately following the completion of the manhole adjustments. Congress (Prentiss - Hayne): Concrete reconstruction is complete. Seeding and fertilizing construction areas underway as well as cleaning of the site.
Mar 27: Congress (Chef Menteur - Prentiss): Paving operations and utility adjustments to start next week. Paving is a moving operation; therefore, intersections within close proximity to the paving machine will be temporarily restricted for 30-45 minutes in addition to the alternating one-lane closures already in place. Congress (Prentiss - Hayne): Concrete curb repair and roadway adjustments continue. Crews to start work-list items and cleaning of the site next week.
Mar 18: Asphalt patching completed today; milling to begin tomorrow, March 19 and continue for the remainder of this week between Chef Menteur and Prentiss. Installation of curb, ADA ramps and concrete replacement continue between Prentiss and Hayne; last segment of concrete installment is scheduled for Friday, March 21.
Mar 7: Installation of ADA ramps between Prentiss and Hayne continue. Concrete placement, utility adjustments and curb repair along the golf course to take place next week. Crews will also place concrete at the corner of Columbia and Congress.
Feb 28: Placement of pavement underway in the southbound lane between Prentiss and Madrid. Next week, crews plan to place pavement in the northbound lane between Frankfort and Columbia. Installation of ADA ramps between Prentiss and Hayne to follow. There will be no construction activities on Mardi Gras, March 4.
Feb 18: (Chef Menteur – Prentiss): Pavement patchwork continues, followed by the curb and utility adjustments next week. Also, Sewerage and Water Board to repair water leaks. (Prentiss – Hayne): Excavation of existing northbound lanes completed, and new base course to be installed this week. Southbound excavation has begun and will continue towards Hayne.
Feb 7: Pavement excavation from Mithra to the golf course, in the northbound lane, to continue next week. Sewerage and Water Board has completed sewer line fixtures between Mexico and Columbia, concrete reconstruction of segment to start next week.
Feb 3: ADA ramp installation, pavement excavation, patchwork and replacement continue this week. Sewerage and Water Board continues sewer line fixtures between Mexico and Columbia.
Jan 30: Road repairs resume, today. Pavement excavation, patchwork and ADA ramp installations continue.
Jan 27: Construction activity limited, this week, due to cold weather conditions. One-lane closures remain effective throughout the construction zone area. Crews will monitior traffic conditions and make changes to traffic cones, barricades and signage as neccessary.
Jan 24: Concrete excavation, patching and replacement to continue next week. ADA ramp installation at sidewalk intersections and Sewerage and Water Board sewer line fixtures will also continue.
Jan 17: The end time for construction work on Congress between Prentiss and Hayne has been extended from 5:30 pm. to 8 pm. Crews may also work weekends between Chef Menteur and Hayne to continue excavation, patching and installation of ADA ramps.
Jan 15: Crews to install ADA ramps between Chef Menteur and Prentiss today. Excavation and the forming of a large patch between Mithra and Odin, scheduled for this week. Expect construction work to take place this weekend as crews place concrete at Prentiss moving towards Hayne.
Jan 9: Congress from Mexico to Hayne is currently closed as Sewerage and Water Board removes and replaces a sewer line. Area will reopen when replacement is complete.
Jan 7: Pavement excavation and saw cutting underway between Mithra and Prentiss. Crews are also performing full reconstruction at Prentiss moving towards Hayne. ADA ramp removal and replacement is also underway at sidewalk intersections.
Jan 5: Road repairs start tomorrow. One-way traffic will be implemented throughout construction.
Dec 26: Given the width of the roadway, the traffic control has been revised to include only one-way traffic throughout the entire project limits, which is Congress between Chef Menteur and Hayne. Construction to start Monday, Jan 6.
Dec 17: Community meeting held at St. Gabriel Archangel Parish Hall to discuss upcoming road repairs to Congress Drive. Traffic control will include one lane closure in each direction between Chef and Prentiss. Only one-way traffic will be permitted throughout construction between Prentiss and Hayne.
Dec 10: A community meeting will be held Tuesday, Dec 17 at 6pm at the St. Gabriel Archangel Parish Hall, 5000 Piety Drive, New Orleans, LA 70126 to discuss upcoming road repairs of Congress Drive.
D3 Extension: W. Esplanade Ave.
West Esplanade Avenue (Williams Boulevard - Power Boulevard)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
April 2: Crews have reached completion of this project. All temporary traffic signage to be removed.
Mar 26: Permanent striping underway. All lanes are open for travel as project nears completion.
Mar 21: Paving of mainline, turn-outs and crossovers are complete. Permanent striping to start next week.
Mar 14: Crews to continue paving turn-outs and cross-overs. Curb repair and sawing and sealing of joints will also occur next week.
Mar 6: Paving continues through Saturday, March 8. Sawing and sealing of joints and curb repair to start next week. Curb repair between the Duncan Canal and Williams Blvd is complete with all lanes open to traffic.
Feb 25: This week, crews continue pavement patching and cold milling operations (2-inch removal of existing pavement). Asphalt paving to start next week. Paving is a moving operation; therefore, intersections within close proximity to the paving machine will be temporarily restricted for 30-45 minutes in addition to the alternating one-lane closures already in place.
Curb repair continues this week between the Duncan Canal and Williams Blvd. Only one lane in one direction remains closed to traffic. The lane will reopen to traffic each day at the end of construction working hours.
Feb 17: Pavement patching continues and cold milling operations (removal of 2 inches of existing pavement) start this week. Curb repair between the Duncan Canal and Williams also starts this week.
Feb 12: Pavement excavation and patchwork continues in the median lanes. Cold milling operations (removal of 2 inches of existing pavement) to start next week. One lane, westbound and eastbound, remains open for travel.
Feb 5: ADA ramp installation complete. Crews continue excavation and patchwork in the median lanes. One lane, westbound and eastbound, remain open for travel.
Jan 30: Road repairs resume, today. Planned excavation and patchwork continues.
Jan 27: Construction activity limited, this week, due to cold weather conditions. One-lane closures remain effective. Crews will monitor traffic conditions and make changes to traffic cones, barricades and signage as necessary. When weather permits, crews to move to the inside lanes to perform pavement excavation and patchwork. ADA ramp installations near completion.
Jan 21: Pavement excavation and patching continue. ADA ramp installation at sidewalk intersections also underway. One lane, westbound and eastbound, is open to traffic.
Jan 13: This week, crews to continue excavation and patching in the outside lane, eastbound and westbound. ADA ramp installation also continues.
Jan 6: Road repairs begin today. Alternating one-lane closures are in effect.
Dec 18: The W. Esplanade extension from Williams Blvd to Power Blvd is scheduled to start January 6, 2014. Only one lane in each direction will be open for travel throughout construction. Repairs include cold milling, pavement patching, curb repair, asphalt overlay and ADA ramp installation. Crews plan to reach completion in April 2014.
D3: Loyola Dr., 31st St., W. Esplanade Ave.
Loyola Drive (W. Esplanade Avenue - 3 Loyola's/Intersection of W. Loyola Drive and E. Loyola Drive)
31st Street (Duncan Canal - Loyola Drive)
W. Esplanade Avenue (Williams Boulevard - Ole Miss Drive)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Dec 18: Resurfacing and striping complete for project segments of W. Esplanade, Loyola and 31st. Crews plan to perform additional curb repair on W. Esplanade from Duncan Canal to Williams, starting January 6, 2014. Only one lane in one direction will be closed during construction hours (westbound and eastbound lanes will not close simultaneously). The lane will reopen to traffic each day after construction working hours. Standard working hours are between 7AM – 5:30PM, Monday - Friday. Crews may extend working hours and work weekends if City grants permission. Curb repair to last 2- 3 weeks.
Dec 9: W. Esplanade (Ole Miss - Williams): Striping of eastbound to resume when weather permits. Striping is a moving operation. All lanes are open for travel. 31st (Duncan Canal - Loyola): Patch repair to resume when weather permits. Alternating lane closures and detour to 30th Street is in place. Loyola (W. Esplanade - 3 Loyola's): Striping of crosswalks to resume when weather permits. Striping is a moving operation. All lanes are open for travel.
Dec 2: W. Esplanade (Ole Miss - Williams): Crews resume temporary closure of the eastbound high lane to complete sawing and sealing joints. Striping to begin Wednesday, Dec 4 and continue through the weekend. All lanes will reopen to traffic during striping operations. 31st (Duncan Canal - Loyola): Paving operations are underway. Alternating lane closures and rolling closures of intersections are in place, and a detour to 30thstreet has been established. Loyola (W. Esplanade - 3 Loyola's): All lanes are open for travel with temporary striping in place.
Nov 25: W. Esplanade (Ole Miss - Williams): Paving is complete, and crews are sealing joints. Roadway to reopen to traffic on Wednesday, Nov 27. Crews to stripe the roadway after the Thanksgiving holiday. Striping will be a moving operation with no cones or barricades. 31st (Duncan Canal - Loyola): Paving to start the week of Dec 2. Alternating lane closures and restriction of intersections lasting up to 45 minutes will be implemented. A detour to 30th street will be in place. Loyola (W. Esplanade - 3 Loyola's): Paving operations are complete. Crews to remove traffic control devices and reopen the roadway to traffic today, Nov 25.
Nov 18: W. Esplanade (Ole Miss - Williams): Paving of the turnouts and crossovers is near completion. 31st (Duncan Canal - Loyola) Cold milling operations to begin tomorrow, Nov 19. Loyola (W. Esplanade - 3 Loyola's): Paving operations to start this week. ADA ramp installation at the intersection of Loyola and W. Esplanade continues.
Nov 13: Paving operations for Loyola (W. Esplanade and 3 Loyola's) to begin Friday, Nov 15. In addition to alternating lane closures, intersections will be temporarily closed for up to 45 minutes. Paving is a moving operation; only intersections within close proximity to the paver will be restricted at a time. Paving to last 5 working days.
Nov 11: W. Esplanade (Ole Miss - Williams): ADA ramp installation and paving of the turnouts, turning lanes and median crossovers continue this week. Crews will also repave the right lane between Williams and Duncan Canal (eastbound and westbound) to meet liquid asphalt specifications. Paving of W. Esplanade to reach completion this week.
31st (Duncan Canal - Loyola): Eastbound lane is closed and traffic is detoured to 30thStreet as the construction of bus pads continue. Crews plan to complete bus pad repairs this week and begin cold milling operations on Monday, Nov 18. Loyola (W. Esplanade - 3 Loyola's Intersection): Cold milling of the southbound lane continues today, Nov 11. This week, crews to install ADA ramps in the southbound lane and at the W. Esplanade and Loyola intersection. Paving operations to start on Friday, November 15.
Nov 8: W. Esplanade (Williams – Ole Miss) Paving of the mainline between Duncan Canal and Ole Miss is complete. Paving of the turn-outs, turning lanes and median cross-overs between Williams and Ole Miss will continue through next week. Crews to start the removal and replacement of the recent asphalt overlay of the right lane (eastbound and westbound) on W. Esplanade between Williams and Duncan Canal on Monday, Nov 11. During the testing process, it was determined that the liquid asphalt did not meet specifications. Crews to cold mill the surface on Monday, November 11 and begin repaving on Wednesday, November 13. Repaving of the segment to last one day.
Nov 4: 31st Street (Loyola - Duncan Canal): Tomorrow, the eastbound lane of 31st Street between Loyola Drive and Duncan Canal will close, and traffic will reduce to one lane. For the next three to four weeks, only one direction of vehicular traffic will be allowed, to facilitate the removal and replacement of bus pads along the corridor. Traffic will be detoured to 30th Street.
W. Esplanade (Williams - Ole Miss): Crews continue paving between Duncan Canal and Ole Miss this week. In addition to one lane closures, temporary closures of side street intersections will close, for up to 45 minutes. Only side street intersections within close proximity to the paver will close at a time. Loyola Drive (W. Esplanade - 3 Loyolas): Cold milling operations to start tomorrow, November 5. ADA ramp installation continues. One lane, in each direction remains open.
Oct 30: Paving of W. Esplanade is rescheduled to begin Friday, November 1, due to the possibility of rain tomorrow. Current road closures will remain effective in addition to rolling closures of cross sections, lasting up to 45 minutes. Only cross sections within close proximity to the paving machine will be closed at a time. Police detail will be on-site to assist with traffic conditions; cross sections will reopen as construction progresses.
Oct 25: W. Esplanade (Ole Miss - Williams): ADA ramp installation, utility adjustments and joint re-sealing is underway. Paving is anticipated to begin Thursday, October 31. Paving will begin between Williams and Duncan Canal. Crews will then pave between Duncan Canal and Ole Miss, starting on Nov 4. Current road closures will remain effective in addition to the cross sections being temporarily closed for up to 45 minutes to allow the new asphalt to cure and harden. Police detail will be on-site to assist with traffic and cross sections will re-open as construction progresses. All dates are dependent on weather and other unforeseen events.
31 Street (Duncan Canal - Loyola): ADA ramp installation is complete. Bus pad repairs are soon underway. Loyola (W. Esplanade - 3 Loyola's Intersection): ADA ramp removal and replacement is underway and will continue next week.
Oct 22: W. Esplanade (Ole Miss - Williams): Pavement patching is complete. Joint re-sealing, utility adjustments and ADA ramp installation is underway. 31st Street (Duncan Canal - Loyola): ADA ramp installation continue. Bus pad repairs are soon underway. Loyola (W. Esplanade - 3 Loyola's Intersection): ADA ramp removal and replacement underway northbound.
Oct 10: Today, crews will temporarily re-open both eastbound lanes of W. Esplanade Avenue between Williams Blvd and the Duncan Canal for 4 - 5 days. One eastbound lane will re-close between Ole Miss and Duncan Canal when curb repair resumes next week. Loyola Drive (W. Esplanade – 3 Loyola’s Intersection): Crews will return to the original plan to construct road repairs on Loyola before the W. Esplanade extension (Williams - Power) project begins. Road closure and traffic signage will be installed today, Oct 10. ADA ramp removal and replacement is soon underway. One lane in each traveling direction will remain open.
Oct 8: W. Esplanade Avenue (Ole Miss - Williams): ADA ramp installation and pavement patching continue eastbound. Patching of the westbound high lane continues. One lane in each traveling direction is open. 31st Street (Duncan Canal - Loyola): ADA ramp installation westbound and eastbound continues. All lanes are currently open to traffic. Loyola Drive (W. Esplanade – 3 Loyola’s Intersection): Road rehabilitation to start when crews complete repairs to W. Esplanade from Ole Miss to Williams and move to the next segment, which is Williams to Power Blvd. One lane in each direction will remain open when construction begins.
Oct 4: No repairs are scheduled for the weekend due to Tropical Storm Karen.
Sept 27: W. Esplanade Avenue (Ole Miss - Williams): Crews are pouring concrete patches in the eastbound low lane today, this weekend and next week. Westbound traffic will switch to the low lane as crews begin patching in the closed, high lane next week. 31st Street (Duncan Canal - Loyola): Crews to install ADA compliant ramps in westbound and eastbound lanes next week. Loyola Drive (W. Esplanade – 3 Loyola’s Intersection): Road rehabilitation to start when crews complete repairs to W. Esplanade from Ole Miss to Williams and move to the next segment, which is Williams to Power Blvd. One lane in each traveling will remain open when construction begins.
Sept 20: W. Esplanade Avenue (Ole Miss – Williams): Crews will begin pouring concrete patches in the westbound lane, next week. Saw cutting and removal of panels and pavement to continue next week, in the eastbound lane. One lane in each traveling direction will remain open. 31st Street (Duncan Canal – Loyola): Crews to continue saw cutting and excavating sidewalk intersections next week. All lanes are open for travel. Loyola Drive (W. Esplanade – 3 Loyola’s Intersection): Road rehabilitation to start when crews complete repairs to W. Esplanade from Ole Miss to Williams and move to the next segment, which is Williams to Power Blvd. One lane in each traveling will remain open when construction begins.
Sept 13: W. Esplanade (Ole Miss - Williams): Eastbound lane from Duncan Canal to Williams Blvd will re-close on Monday, September 16 to allow pavement excavation. Pavement patching and ADA ramp installation will continue next week in the westbound lane also. 31st (Duncan Canal - Loyola): Pavement patching and ADA ramp installation will continue next week. Loyola (W. Esplanade - 3 Loyola's Intersection): Repairs will take place in upcoming weeks.
Sept 9: Crews have opened the eastbound lane of W. Esplanade Avenue between Duncan Canal and Williams to help alleviate traffic conditions
Sept 6: Traffic control and signage have been installed. Road repairs are underway. The following work will begin Monday, Sept 9. Loyola Drive (W. Esplanade - 3 Loyola’s Intersection): Pavement demolition and ADA ramp excavation. 31st Street (Duncan Canal - Loyola Drive): Pavement demolition and ADA ramp excavation. W. Esplanade Avenue (Ole Miss – Williams): Saw cutting of roadway. W. Esplanade Avenue (Williams – Power): Repairs will begin in upcoming weeks.
Sept 5: Crews begin placing traffic control and signage in preparation of road repairs. One lane in each travel direction will remain open on Loyola Drive and 31st Street. Construction work will begin Monday, Sept 9.
Sept 3: W. Esplanade Avenue project limits will now extend from Power Boulevard to Ole Miss Drive. Previous plans only included W. Esplanade Ave from Williams Blvd to Ole Miss Dr.
Aug 29: Project road rehabilitation to begin next week.
Aug 20: Neighborhood informational meeting held at 6 p.m. at Kenner City Park Pavilion to discuss upcoming road repairs.
Aug 13: Neighborhood informational meeting to be held on Tuesday, August 20 at 6 p.m. at Kenner City Park Pavilion to discuss upcoming roadway rehabilitation.
D2: Sal Lentini Pkwy, Chateau Blvd., Joe Yenni Blvd.
Sal Lentini Parkway (Joe Yenni Boulevard - Vintage Drive)
Chateau Boulevard (Vintage Drive - Chateau Du Lac)
Joe Yenni Boulevard (Williams Boulevard - Sal Lentini Boulevard)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Sept 4: Crews reached substantial completion of project. Contractor has 30 days to complete permanent striping.
Aug 29: Repairs on Joe Yenni at the Gabrielle turn lane are underway. Crews are also installing loop detectors on Joe Yenni and Sal Lentini. A final walk-through of this project is tentatively planned for next week.
Aug 22: Sal Lentini Parkway (Joe Yenni - Vintage): Paving is complete. Crews continue curb and gutter re-construction. Chateau Boulevard (Vintage - Chateau Du Lac): Crews continue work on minor detailed items. Joe Yenni Boulevard (Williams - Sal Lentini): Cleaning and re-sealing operations underway.
Aug 15: Sal Lentini Parkway (Joe Yenni - Vintage): Paving of the mainline is complete. Crews to continue paving the turnouts near Williams and Moselle next week. Chateau Boulevard (Vintage - Chateau Du Lac): Mainline paving to be complete tomorrow, August 16. Joe Yenni Boulevard (Williams - Sal Lentini): Paving of the mainline is complete. Crews to continue patch work and paving of the turnouts next week.
Aug 6: Sal Lentini Parkway (Joe Yenni - Vintage): Reconstruction of curb and gutter continues. Asphalt overlaying projected to begin Friday, August 9. Chateau Boulevard (Vintage - Chateau Du Lac): ADA-ramp installation continues. Joe Yenni Boulevard (Williams - Sal Lentini): Asphalt overlaying in progress; Paving to be complete by Thursday, August 8.
Jul 31: Sal Lentini Parkway (Joe Yenni - Vintage): Milling is complete. Curb and gutter bottom repairs underway this week. Chateau Boulevard (Vintage - Chateau Du Lac): Milling is complete. Curb and gutter bottom repairs continue. Joe Yenni Boulevard (Williams - Sal Lentini): Milling is complete. Concrete panel repairs to be complete by Friday, August 2.
Jul 23: Sal Lentini Parkway (Joe Yenni - Vintage): Milling is complete. Crews are working on curb & gutter repairs this week. Chateau Boulevard (Vintage - Chateau Du Lac): Mainline milling to reach completion today. Turnouts and crossovers will follow the rest of this week. Joe Yenni Boulevard (Williams - Sal Lentini): Milling complete from Sal Lentini to Duncan Canal. Concrete panel repair underway from Duncan Canal to Williams.
Jul 19: Cold milling on Sal Lentini Pkwy is complete. Milling of Joe Yenni Blvd is scheduled for completion today. Crews are saw cutting and removing concrete on Joe Yenni Blvd. Milling of Chateau Blvd to begin Monday, July 22.
Jul 17: Crews begin cold milling on Sal Lentini Parkway from Joe Yenni Boulevard to Vintage Drive. Sal Lentini Parkway (Joe Yenni - Vintage): Both right lanes are closed northbound and southbound. Chateau Boulevard (Vintage - Joe Yenni): Both right lanes are closed northbound and southbound. Joe Yenni Boulevard (Williams - Chateau): Both right lanes are closed eastbound and westbound.
Jul 15: Traffic Control and signs will be installed tomorrow in preparation of the start of construction. Cold milling operations will start on Wednesday, July 17.
June 5: Neighborhood informational meeting held at 6:00 pm at Kenner City Park Pavilion to discuss upcoming roadway rehabilitation.
May 29: Neighborhood informational meeting to be held on Wednesday, June 5 at 6:00 p.m. at Kenner City Park Pavilion to discuss upcoming roadway rehabilitation.
D1: Vintage Dr. and Loyola Dr.
Vintage Drive (Loyola Drive - Duncan Canal)
Loyola Drive (Vintage Drive - W. Esplanade Avenue)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Aug 9: Kenner Department of Public Works to install a new permanent generator at the lift station near the Vintage and Medoc intersection; a second project involves the installation of a new larger force main from that same station. A portion of east-bound Vintage Drive was intentionally left incomplete by the Paths to Progress contractor to ensure that the roadway would not be evacuated after the repavement. Instead, this pavement work will be performed by the Vintage and Medoc Force Main contractor. For any information on this construction project in Kenner, please contact the Public Works Department at (504) 468-7515.
Aug 8: DOTD Secretary Sherri LeBas receives key to the City of Kenner at the ribbon-cutting ceremony held at Kenner City Park Pavilion. She was joined by state and local officials, including Mayor Yenni.
Aug 2: Ribbon-cutting ceremony to be held on Thursday, August 8 at 10:30 a.m. at Kenner City Park Pavilion to celebrate the project completion.
Jul 30: Completion of striping rescheduled for Friday, August 2.
Jul 23: Striping on Vintage & Loyola began today with a completion date of July 29.
Jul 19: Permanent striping rescheduled to begin on Tuesday, July 23.
Jul 17: Lanes are now open on Vintage and Loyola. Remaining construction cones will be removed.
Jul 15: Crews reach substantial completion today. Permanent striping begins Monday, July 22nd.
Jul 8: Paving on Loyola and Vintage is complete. Crews continue to work on minor punch list items.
Jun 25: Vintage Drive (Loyola - Duncan Canal): Asphalt paving on Vintage is complete. Crews are saw cutting and sealing joints in eastbound lanes, repairing areas in eastbound & westbound lane and finishing punch list items from Loyola to Duncan Canal. Crews begin cleaning northbound and southbound lanes on Loyola as punch list items work continues. Asphalt paving on Loyola is complete.
Jun12: Eastbound lane of Vintage Drive between Medoc and Chateau to be closed June 13 and 14 as part of the City Kenner Department of Public Works project. Project is separate from the P2P program.
Jun 6: Vintage Drive from Normandy Drive to Chateau Boulevard will be temporarily closed during paving operations starting within in 30 minutes. Traffic will be detoured onto Normandy Dr. and then to Chateau Blvd. Road closure will reopen this afternoon.
May 17: Loyola Drive: ADA ramp installation and pavement patching continue. Patching the intersection of Loyola and Vintage to begin Monday, May 20. Vintage: Installation of ADA ramps and pavement patching to continue next week. Roadway leveling and paving projected to begin Monday, May 27.
April 19: Cold milling on Loyola Drive begins
April 15: Installation of ADA-compliant ramps begins
March 5: Neighborhood informational meeting held on Tuesday, March 5 at 6:00 p.m. at Kenner City Park Pavilion to discuss upcoming roadway rehabilitation.
C3: Jefferson Davis Pkwy., Banks St., Bienville Ave.
South Jefferson Davis Parkway (Gravier Street – Canal Street)
Banks Street (S. Carrollton Avenue - St. Patrick Street)
Bienville Avenue (Jefferson Davis Parkway – N. Carrollton Avenue)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. The installation of bike lanes is also included in this project. A dedicated bike lane will be installed, in each direction, on Banks Street. The area between S. Carrollton and S. Hennessey will remain a two-travel lane to accommodate the traffic near Jesuit High School. Other segments of the repaved roadway will include a dedicated bike lane. *The scope of work does not include sidewalk or driveway repairs.
Jul 7: Removal and replacement of the concrete approach slabs on S. Jefferson Davis Pkwy is complete. Installment of barrier walls is underway. The bicycle path and northbound lane will re-open to traffic today. Southbound lane to re-open to traffic later this week.
May 12: Removal and replacement of the concrete approach slabs of the southbound lanes of S. Jefferson Davis Pkwy at the I-10 overpass begin this week. Today, crews are setting up the traffic signage, cones and barricades for the temporary closures of S. Jefferson Davis Pkwy at the I-10 overpass between Tulane and Palmetto. The temporary closures and detours are expected to last five to six weeks.
May 5: Temporary closures of S. Jefferson Davis Pkwy at the I-10 overpass have been rescheduled to start on Monday, May 12. The temporary closures will last five to six weeks.
May 2: Temporary closures of South Jefferson Davis at I-10 overpass to start on Monday. Crews will perform repairs to S. Jefferson Davis Pkwy at the I-10 overpass, starting on Monday, May 5 and lasting five to six weeks. Temporary closures will facilitate the removal and replacement of the concrete approach slabs. There will be a temporary closure of South Jefferson Davis Parkway southbound lanes at the I-10 overpass from Tulane Avenue to Palmetto Street. Traffic will be detoured to South Broad Street at the I-10 overpass. Also, the left northbound lane of South Jefferson Davis Parkway at the I-10 overpass from Palmetto Street to Tulane Avenue will temporarily close to vehicular traffic and convert into a bike path for cyclists. The right northbound lane of South Jefferson Davis Parkway will remain open to traffic throughout construction. The improvements are a continuation of the South Jefferson Davis Pkwy project that began in November 2013.
April 7: Final walk-through of project held Friday, April 4. Crews to remove temporary traffic signage, clean site, seed and fertilize construction areas and complete other punch list items.
Mar 21: Road repairs including pavement removal, patching and resurfacing are complete for all street segments. ADA ramp installation and permanent striping complete as well. Crews to install bike symbols on Banks Street this weekend and complete work-list items for all street segments next week. All lanes are open for travel on Banks, Bienville and S. Jefferson Davis.
Mar 13: Banks (S. Carrollton – St. Patrick): Asphalt corrections continue. Permanent striping to start tomorrow, March 14. The segment between S. Carrollton and S. Hennessey will remain a two-travel lane, with the right lane being a shared bike lane, to assist the traffic near Jesuit High School. Other segments of the repaved roadway will include a dedicated bike lane.
S. Jefferson Davis (Gravier – Canal): Permanent striping complete. Crews to remove the temporary "no parking” signs and install bike symbols and signage for the shared bike lane. All lanes are open for travel, and on-street parking is available. Bienville (Jefferson Davis – N. Carrollton): All lanes are open for travel, and on-street parking is available.
Mar 7: Banks (S. Carrollton – St. Patrick): Removal and replacement of deficient asphalt underway and to continue next week. Locations of asphalt corrections are near the South St. Patrick intersection and the segment between South Hennessey and South Solomon. Permanent striping to follow. All lanes will reopen to traffic immediately following the completion of permanent striping.
S. Jefferson Davis (Gravier – Canal): Permanent striping underway and to continue Saturday, March 8. The one-lane closure will reopen to traffic immediately following the completion of permanent striping. Bienville (Jefferson Davis – N. Carrollton): All lanes are open for travel. On-street parking is available.
Feb 26: Banks (S. Carrollton – St. Patrick): Removal and replacement of deficient asphalt at the contractor’s cost to take place tomorrow. The locations of asphalt replacement are near the S. St. Patrick intersection and the segment between S. Hennessey and S. Solomon. Permanent striping will also begin tomorrow. All lanes will reopen to traffic immediately following the completion of permanent striping.
S. Jefferson Davis (Gravier – Canal): Paving of turnouts and permanent striping to resume tomorrow. The one-lane closure will reopen to traffic immediately following the completion of permanent striping. Bienville (Jefferson Davis – N. Carrollton): All lanes are open for travel. On-street parking will be available by Friday, Feb 28. Crews to begin removing parking restriction signs tomorrow, Feb 27.
Feb 21: Permanent striping to start on Bienville, Friday 21 and continue over the weekend.
Feb 20: Asphalt paving of mainline and cross-overs is complete on S. Jefferson Davis Pkwy. Paving of turn-outs will continue next week, followed by the striping layout. Work-list items are underway on Banks and Bienville to be followed by permanent striping.
Feb 13: Asphalt paving and striping layout of Banks and Bienville is complete. Paving operations start tomorrow, Feb 14, on S. Jefferson Davis Pkwy. Paving is a moving operation; therefore, intersections within close proximity to the paving machine will be temporarily restricted for 30-45 minutes in addition to the alternating one-lane closures already in place.
Feb 10: Paving of Banks mainline is complete. Crews continue to pave turn-outs today, February 10. Paving to start mid-week on S. Jefferson Davis Pkwy, weather pending. Paving is a moving operation; therefore, intersections within close proximity to the paving machine will be temporarily restricted for 30-45 minutes in addition to the alternating one-lane closures already in place.
On Bienville, Work list items and striping layout are underway. Permanent striping to follow. One lane, in each direction, remains open for travel.
Feb 3: Paving of the travel lane, turn-outs and crossovers on Banks (S. Carrollton – St. Patrick) to resume tomorrow, weather pending. Crews to continue performing work list items on Bienville (Jefferson Davis – N. Carrollton) this week. And curb repair, ADA ramp installation and sealing of roadway ruptures continue this week.
Jan 30: Road repairs resume, today. Pavement excavation, patchwork and ADA ramp installation continue. Planned paving operations will start when temperatures are warm enough to allow the new asphalt to be properly placed and compacted.
Jan 27: Construction activity limited, this week, due to cold weather conditions. One-lane closures remain effective. Crews will monitior traffic conditions and make changes to traffic cones, barricades and signage as neccessary.
Jan 22: Banks (S. Carrollton – St. Patrick): Pavement patching and density testing are underway. Paving to start mid-next week. Crews will first pave the median lanes, and then pave the outside lanes. Paving is a moving operation; therefore, intersections within close proximity to the paving machine will be temporarily restricted for 30-45 minutes in addition to the alternating one-lane closures already in place.
Bienville (Jefferson Davis – N. Carrollton): Paving is complete for travel lanes, crossovers and turnouts. Crews to perform work list items this week and next. One lane, in each direction, is open for travel. S. Jefferson Davis (Gravier – Canal): Curb repair and ADA ramp installation are underway. Crews to resume sealing large roadway ruptures next week. One lane, in each direction, remains open for travel.
Jan 15: Two additional water leaks have been reported at 4316 and 4328 Banks. Sewerage and Water Board to repair waterline so that patching may continue. Paving operations for Banks (S. Carrollton - St. Patrick) are postponed until patchwork is complete. Paving of travel and parking lanes on Bienville are complete. Crews to start paving the cross-overs and turn-outs on Bienville (Jefferson Davis - N. Carrollton) before Friday, Jan 17. Sealing of large roadway ruptures continue on S. Jefferson Davis. Installation of ADA ramps and patching near completion on S. Jefferson Davis (Gravier - Canal).
Jan 13: The median lane in each direction of Bienville has been paved. Paving of the outside lanes to start and finish this week. Paving is a moving operation. Intersections within close proximity to the paver will be temporarily restricted for 30-45 minutes in addition to alternating lane closures. Crews to start paving on Banks immediately following the completion of Bienville, which is scheduled for late this week/early next week. This week, crews will start sealing large roadway roadway ruptures on S. Jefferson Davis and continue ADA ramp installation and pavement patching.
Jan 7: Paving of Bienville rescheduled due to cold weather conditions. Outdoor temperatures are too cold to allow the hot mix asphalt to be properly placed and compacted. Crews plan to start paving on Thursday, January 9, weather permitting. ADA ramp installation and pavement patching continue on S. Jefferson Davis and Banks. Water leak reported at 4326 Banks - Sewerage and Water Board to repair.
Jan 2: ADA ramp installation and patching continue on S. Jefferson Davis and Banks. The Sewerage and Water Board is performing a waterline replacement at the S. Jefferson Davis and Banks intersection. Paving of Bienville to start the week of January 6.
Dec 27: Road repairs to resume the week of Dec 30. Pavement patching and ADA ramp installation will continue on Banks and S. Jefferson Davis. Paving of Bienville to begin January 6.
Dec 19: Paving of Bienville rescheduled to start January 6, 2014. Intersections within close proximity will be temporarily restricted for 30 - 45 minutes in addition to alternating lane closures.
Dec 17: Bienville (Jefferson Davis – N. Carrollton): Paving to begin tomorrow, Dec 18. Intersections within close proximity to the paver will be restricted for 30 - 45 minutes at a time in addition to alternating lane closures. Banks (S. Carrollton – St. Patrick): Pavement patching and ADA ramp installation continue this week. Paving to start after the Christmas holiday. One lane in each direction remains open. S. Jefferson Davis (Gravier – Canal): ADA ramp installment and pavement patching continue. One lane in each direction remains open.
Dec 2: Pavement patching, ADA ramp installation and curb repair continue this week on S. Jefferson Davis Parkway, Banks Street and Bienville Avenue. One lane in each direction remains open for all street segments.
Nov 21: S. Jefferson Davis (Gravier – Canal): Cold milling and ADA removal and replacement are underway. ADA ramp installation, patching and curb replacements to continue next week. Banks (S. Carrollton – St. Patrick): Cold milling is complete. ADA ramp installation along with pavement removal and replacement are underway and to continue next week. Bienville (Jefferson Davis – N. Carrollton): Pavement patching and ADA ramp removal and replacement continue.
Nov 13: S. Jefferson Davis (Gravier – Canal): ADA ramp removal and replacement continues. Cold milling to start the week of Nov 18. Banks (S. Carrollton – St. Patrick): Crews begin cold milling today, Nov 13. ADA ramp removal and replacement is also underway. Bienville (Jefferson Davis – N. Carrollton): Cold milling is complete. ADA ramp removal and replacement underway. Pavement patchwork to follow.
Nov 6: Road closures and traffic control start today. One lane in each direction will remain open. Crews to start pavement excavation on Banks (S. Carrollton - St. Patrick) and S. Jefferson Davis (Gravier - Canal) tomorrow. The removal of two inches of asphalt (cold milling) on Bienville (Jefferson Davis - N. Carrollton) to start on Friday, Nov 8.
Nov 3: Project to begin this week, following substantial completion of the Fontainebleau, Freret & Nashville project. Road closures will soon start. One lane, in each direction, will remain open to traffic, on all street segments, throughout construction.
Oct 24: Program officials hold the neighborhood informational meeting at Jesuit High School to discuss upcoming repairs, starting in November.
Oct 17: Neighborhood informational meeting to be held on Thursday, Oct 24 at 6:00 p.m. at Jesuit High School, St. Ignatius Hall, Third Floor, 4133 Banks Street, New Orleans, LA 70119 to discuss upcoming roadway rehabilitation.
C2: Freret St., Nashville Ave., Fontainebleau Dr.
Freret Street (Louisiana Avenue – Jefferson Avenue)
Nashville Avenue (S. Claiborne Avenue - Fontainebleau Drive)
Fontainebleau Drive (Broadway Street – Nashville Avenue)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
*Nashville Avenue from S. Claiborne to Fontainebleau will be restriped as one travel lane, bicycle lane and parking lane in both directions.
Jul 9: Temporary closure of Fontainebleau Drive between Nashville Avenue and Broadway Street, scheduled to start on Wednesday, July 9 and last through Friday, July 11. The temporary closure will facilitate pavement removal and replacement. A detour will be established. Please use alternative routes, including South Claiborne Avenue.
Dec 3: Today, crews returned to Nashville to install bike symbols and signage
Nov 6: Crews have reached substantial completion of this project, and striping is complete. Crews plan to install bike symbols on Nashville Avenue within 30 days.
Oct 29: Freret (Louisiana – Napoleon): Paving is underway in high lane. Asphalt overlay to be complete within days. Freret (Napoleon – Jefferson): Paving is complete. Crews are inspecting site and removing construction debris. Striping to follow. Fontainebleau (Broadway – Nashville): Paving is complete. Removal of excess asphalt and construction debris is underway along with minor work list items. Nashville (S. Claiborne – Fontainebleau): Median curb repair underway in addition to minor working items.
Oct 23: Paving of Freret Street between Napoleon and Jefferson to begin tomorrow, Oct 23. Paving will begin at Napoleon and move towards Jefferson.
Oct 16: Fontainebleau (Broadway - Nashville): Paving operations to begin tomorrow, Oct 17. Crews will begin full closure of the eastbound lane of Fontainebleau from Broadway to Nashville. When paving crews reach Nashville and moves toward Broadway, the westbound lane will close. Alternating closures will be effective Thursday, Oct 17 between 7 a.m. and 5:30 p.m. Roadway segments will reopen to cross traffic as construction progresses.
Freret (Louisiana - Napoleon): Bus pad repairs, stone curb resetting, ADA ramp installation continue. Freret (Napoleon - Jefferson): Pavement patching continues this week. Nashville: Paving of mainline is complete. Crews continue to pave the turn-outs. Additional patchwork to follow.
Oct 9: Fontainebleau (Broadway - Nashville): Curb repairs, ADA ramp installation and patching continue. Paving will begin when the asphalt overlay of Nashville is complete.
Freret (Louisiana - Napoleon): Stone curb resetting, bus pad repairs and patching to continue through next week. Freret (Napoleon - Jefferson): Milling is complete. Crews are pavement patching and performing manhole adjustments throughout next week. Nashville (S. Claiborne - Fontainebleau): Paving to start Friday, October 11. Paving will begin at S. Claiborne and move towards Fontainebleau.
Oct 2: Fontainebleau (Broadway – Nashville): Curb repairs, ADA ramp installation and pavement patching underway. Freret (Louisiana – Napoleon): Stone curb resetting and bus pad repairs continue.
Freret (Napoleon – Jefferson): Milling delayed due to weather conditions. Milling will begin tomorrow, October 3, if weather permits. Only one travel lane in one direction will remain open throughout construction. Nashville (S. Claiborne – Fontainebleau): Curb repair and reset underway. Paving to begin by Thursday, October 10.
Sept 26: Fontainebleau (Broadway – Nashville): Curb and gutter repairs underway and to continue next week. Freret (Louisiana – Napoleon): Pavement patching, stone curb resetting, bus pad repairs to continue next week. Freret (Napoleon – Jefferson): Cold milling to begin Monday, Sept 30 or Tuesday, Oct 1. Only one travel lane in one direction will remain open throughout construction.
Nashville (S. Claiborne – Fontainebleau): Milling to be complete this week. Curb and gutter repairs begin Monday, Sept 30.
Sept 18: Fontainebleau (Broadway – Nashville): Curb and gutter repair, pavement patching and ADA ramp installation underway. Freret (Louisiana – Napoleon): Pavement patching, stone curb resetting, curb and bus pad repairs along with ADA ramp installation continue.
Freret (Napoleon – Jefferson): Cold milling rescheduled to begin the week of September 30, when milling of Nashville is complete. Only one travel lane in one direction will remain open when construction starts. Nashville (S. Claiborne – Fontainebleau): Pavement patching and ADA ramp installation underway. Grade elevations are complete and milling will begin Monday, September 23.
Sept 11: Fontainebleau (Broadway – Nashville): Bus pad and median curb repairs underway. Patching to begin next week. Freret (Louisiana – Napoleon): ADA ramp installation and curb repairs continue. Pavement patching and stone curb resetting to begin next week.
Freret (Napoleon – Jefferson): Cold milling to begin the week of September 23, immediately after the milling of Nashville is complete. Only one travel lane in one direction will remain open when construction starts. Nashville (S. Claiborne – Fontainebleau): ADA ramp installation and grade elevations continue. Cold milling and patching to begin when elevations are complete. One travel lane in each direction remains open.
Sept 4: Fontainebleau (Broadway – Nashville): Cold milling is complete. Curb replacement continues. Bus pad repairs are soon underway. One travel lane in each direction remains open. Freret (Louisiana – Napoleon): Cold milling is complete. ADA ramp installation and curb repair underway. Pavement patching to follow. Only one travel lane in one direction remains open.
Freret (Napoleon – Jefferson): Cold milling to begin in 2 – 3 weeks, following the milling of Nashville. Only one travel lane in one direction will stay open when construction begins. Nashville (S. Claiborne – Fontainebleau): Crews are testing grades in preparation of milling. Cold milling and curb replacement is soon underway. ADA ramp installation continues. One travel lane in each direction remains open.
Aug 28: Fontainebleau (Broadway – Nashville): Cold milling is complete. Curb reset along with curb and gutter repairs are underway, with one travel lane in each direction remaining open. Freret (Louisiana – Napoleon): Cold milling and ADA ramp demolition and replacement are underway, with only one travel lane in one direction remaining open.
Freret (Napoleon - Jefferson): Construction work to begin in 3-4 weeks, following the cold milling of Nashville. Only one travel lane in one direction will remain open. Nashville (S. Claiborne – Fontainebleau): Pavement patching and demolition of existing ADA ramps are underway, with one travel lane in each direction remaining open.
Aug 22: Work officially begins on the Nashville, Fontainebleau and Freret project.
Aug 21: Prep work such as tree trimming and curb inlet protection has begun and will continue this week. Construction work is yet to begin as crews are completing punch list items on Broadway and Leonidas.
Aug 14: Cold milling (removing 2 inches of asphalt) on Fontainebleau to begin Monday, August 19. One travel lane in each direction will remain open. Monday will also be the start of pavement patching and installing ADA-compliant ramps on Nashville. One travel lane in each direction will remain open.
Pavement patching and installing ADA-compliant ramps on Freret to begin Monday, August 19. Crews will begin work at the eastern side of Freret from Louisiana to Napoleon. Starting at the less congested side (Louisiana – Napoleon) will allow the Sewerage and Water Board to complete the waterline replacement and the Department of Public Works to re-install the deficient ADA ramps along the corridor. Traffic control for the Freret (Napoleon - Jefferson) segment will not be enforced until crews reach that area.
Aug 7: Project is expected to begin Thursday, August 15. Crews will notify businesses, schools and residents with a letter of intent tomorrow (7 days prior to the start of construction).
Jul 31: Construction is proposed to begin August 12, 2013 and reach substantial completion by November 2013. Weather and unforeseen events pending.
Jul 30: Neighborhood informational meeting held at Tulane University Campus, Lavin-Bernick Center, Building 29, Stibbs Conference Room #203 to discuss upcoming roadway rehabilitation.
Jul 23: Neighborhood informational meeting to be held on Tuesday, July 30 at 6:00 p.m. at Tulane University Campus, Lavin-Bernick Center, Building 29, Stibbs Conference Room #203 to discuss upcoming roadway rehabilitation.
C1: Leonidas St. and Broadway St.
Leonidas Street (Palmetto Street - Earhart Boulevard)
Broadway Street (Fontainebleau Drive - Leake Avenue)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Sept 20: Striping is complete. Parking restriction signs have been removed and all roadways are open for travel.
Sept 18: Permanent striping to be complete Friday, September 20. The "no parking" signs will be removed by 5:00 p.m. on Friday. On-street parking will resume at it was prior to the start of construction.
Aug 26: Crews have reached substantial completion. Permanent striping is underway and will include a shared bike lane on Broadway from Fontainebleau to Leake. Crews have 30 days to complete permanent striping.
Aug 21: A final walk-through took place for this project on Tuesday, August 20. It was determined that a number of punch list items must be complete before proceeding the next subgroup. The completion of punch list items should not exceed 7 calendar days.
Aug 14: The 1600 block area of Broadway has been repaved. Crews continue to work on minor detailed-items on Broadway and Leonidas. Project substantial completion is expected no later than Friday, Aug. 16 Weather and unforeseen events pending.
Aug 7: Project substantial completion date is expected Wednesday, August 14. The water leak at 1620 Broadway Street will be repaired by the Sewerage and Water Board and the damaged area will be repaved by Paths to Progress.
Jul 31: Crews will begin a full closure of the riverbound lane of Broadway, from St. Charles to Leake, beginning Thursday, August 1. The closure will switch to the lakebound lane once the paving crews reach Leake and begin paving to St. Charles. The alternating closures will be in effect from Thursday, August 1 through Saturday, August 3, and Monday, August 5, from 7 a.m. to 5:30 p.m.
Jul 26: Broadway (Fontainebleau - Leake): Paving of southbound travel and parking lanes are complete from Fontainebleau to St. Charles. Northbound travel lane complete. Crews continue paving parking lane from Zimple to Fontainebleau tomorrow. Leonidas (Palmetto - Earhart) Paving will be completed today.
Jul 25: Broadway (Fontainebleau – Leake): Paving on the top lanes from Fontainebleau to St. Charles is complete. Crews are now paving the parking lanes from Fontainebleau to St. Charles. Leonidas (Earhart – Palmetto): Paving operations are scheduled for completion tomorrow.
Substantial completion is projected the week of August 5, 2013. Weather and unforeseen events pending.
Jul 23: Crews will begin a full closure of the southbound lane of Broadway, from Fontainebleau to St. Charles, beginning today at 7 a.m. The closure will switch to the northbound lane once the paving crews reach St. Charles and begin paving to Fontainebleau. The alternating closures will be in effect from Tuesday, July 23, through Friday, July 26, from 7 a.m. to 5:30 p.m.
Due to an equipment malfunction, paving operations discontinued at 1:00 p.m. on Tuesday, July 23. Paving will resume tomorrow at 7:00 a.m. Broadway (Fontainebleau - Claiborne) top lane is paved and open to traffic.
Jul 22: Paving operations have been rescheduled due to potential bad weather.
Jul19: Monday morning, July 22, crews will begin a full closure of the southbound lane of Broadway, from Fontainebleau to St. Charles, beginning at 7 a.m. The closure will switch to the northbound lane once the paving crews reach St. Charles and begin paving to Fontainebleau. The alternating closures will be in effect from Monday, July 22, through Friday, July 26, from 7 a.m. to 5:30 p.m.
Jul 17: Surface leveling on Broadway from Fontainebleau to St. Charles is projected to start tomorrow.
Jul 11: Broadway Street (Fontainebleau – Leake): Installation of ADA ramps and median walks continue. Crews are also working on the concrete curb and gutter sections, bus pad repairs and preparing for the asphalt overlay. Leonidas Street (Palmetto - Earhart): Work is at a standstill to accommodate the ongoing Sewerage and Water Board project.
Jul 1: Cold milling on Broadway from Claiborne to St. Charles in the travel lane. Concrete curb and gutter sections repairs, ADA ramp installation at bull noses, pavement patches and bus pad repairs continue on Broadway. ADA ramp installation continues on Leonidas.
Jun 18: Cold milling on the top lanes of Broadway Street will begin tomorrow, June 19. Milling sequence is from Fontainebleau to Claiborne.
Jun 3: The riverbound lane of Broadway Street at Claiborne is temporarily closed as part of a Sewerage and Water Board project. This is a project distinctively different from the Paths to Progress program.
May 20: Leonidas Street (Palmetto Street - Earhart Boulevard): Installation of ADA ramps and pavement patching continue. Cold milling, stone curb resetting and concrete curb removal and replacement underway. Broadway Street (Fontainebleau Drive - Leake Avenue): Installation of ADA ramps and pavement patching continue. Cold milling and concrete curb removal and replacement underway
May 14: Fleming Construction has closed the riverbound lanes at the 2200 block of Broadway Street as part of a New Orleans Sewerage & Water Board waterline repair project. This project is distinctly different from the Paths to Progress program.
May 8: In order to complete a water service project, New Orleans Sewerage and Water Board has temporarily closed Broadway Street southbound from Oak Street to Freret Street. Staff of New Orleans Sewerage & Water are working as quickly as possible to limit the inconvenience to travelers, businesses and schools in the surrounding area. This is a distinctly different project from the Paths to Progress program.
April 18: Cold milling construction on Broadway Street will begin Monday, April 22nd. One lane in each traveling direction will remain open to traffic to ensure a smooth traffic flow. Parking will be restricted during cold milling & pavement operations (6:00 am to 6:00 pm).
April 17: Installation of ADA-compliant ramps begins.
Jan. 31: Neighborhood informational meeting held on Thursday, Jan. 31 at 6:00 p.m. at Tulane University Campus, Lavin-Bernick Center, Building 29 McAlister Way to discuss upcoming roadway rehabilitation.
B3: Basin St.
Basin Street (Canal Street - N. Claiborne Avenue)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Dec 4: Crews have reached substantial completion of project. Permanent striping and installation of bike symbols to be complete before Friday, Dec 6. A ribbon-cutting will be held to celebrate the completion of repairs on Friday, Dec 6 at the Basin St. Station (501 Basin Street, New Orleans, LA 70112).
Dec 2: Permanent striping is underway.
Nov 26: Crews to backfill and seed areas of construction tomorrow, Nov 27. Crews will be off for the Thanksgiving holiday and return to work on Monday, Dec 2. Striping to take place next week.
Nov 20: The paving operations are complete. Crews are performing utility adjustments and gutterline repairs. Layout of striping to follow.
Nov 11: Paving of the parking lanes, crossovers, turnouts, and turn lanes continue this week. Installation of median ADA ramps is also underway.
Nov 6: Paving is underway. Crews began at N. Claiborne Avenue and are moving towards Canal Street. In addition to current lane closures, intersections will be temporarily restricted between 20 - 45 mins. Only intersections within close proximity to the paver will be effected.
Nov 1: Pavement patching and ADA ramp installation continue. Paving to begin Wednesday, November 6. The asphalt overlay will begin at N. Claiborne Avenue and move towards Canal Street.
Current lane closures will remain effective in addition to temporary side street intersections closures, lasting up to 45 minutes. Paving is a moving operation, so only the side street intersections within close proximity to the paving machine will be closed at a time.
Oct 30: Paving to begin mid-next week.
Oct 28: Crews to install ADA ramps along the corners of the parking lane this week. Pavement excavation and patching is also underway.
Oct 22: There will be a temporary closure located at the off ramp of Basin Street and Interstate 10 East scheduled for today, October 22, from 9 am to 1 pm. The closure will allow crews to perform milling operations, clean debris, cold mix joints, and then reopen the ramp. Traffic will be detoured to the Esplanade Avenue off-ramp during the closure.
Oct 17: Crews are installing traffic control. Only one lane in each direction will remain open throughout construction. Cold milling begins tomorrow, Oct 18, at N. Claiborne moving towards Canal Street.
Oct 14: Road repairs will begin this week, immediately following the substantial completion of the Gentilly and St. Bernard project. The two outside lanes, in each direction, wll close as crews start repairs. The lane closest to the median, in each direction, will remain open. One lane in each direction will remain open throughout construction.
Oct 11: Basin Street road closures will begin the week of October 14. The two outside lanes, in each direction, will close as crews start repairs. The lane closest to the median, in each direction, will remain open. One lane in each direction will remain open throughout construction.
Oct 7: Immediately following the substantial completion of the Gentilly and St. Bernard project, crews will begin road repairs on Basin Street. One lane in each traveling direction will remain open throughout construction.
Sept 26: Neighborhood informational meeting held at Treme Rec Center to discuss upcoming road repairs. Work is expected to begin October 7, starting at the N. Claiborne Avenue end.
Sept 20: Neighborhood informational meeting to be held on Thursday, Sept. 26 at 6:00 p.m. at Treme Recreational Center, 900 N. Villere Street, to discuss upcoming roadway rehabilitation.
B2: St. Bernard Ave. and Gentilly Blvd.
St. Bernard Avenue (N. Rampart Street - Sere Street)
Gentilly Boulevard (Paris Avenue - N. Broad Street)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Nov 20: The permanent striping and installation of bike symbols are complete.
Nov 7: Striping to continue tomorow through next week.
Nov 4: Permanent striping begins today, Nov 4. St. Bernard Ave will reduce to one travel lane, with the addition of a dedicated bike lane. The striping will also include a dedicated bike lane on Gentilly Blvd.
Oct 25: Crews are striping the layout to include bike lanes on Gentilly Blvd and St. Bernard Ave project limits. Permanent striping to follow upon approval.
Oct 17: Crews have reached substantial completion. Permanent striping to be complete within 30 days.
Oct 14: Final punch list items were determined in today's final walk through. Crews will reach substantial completion and re-open street segments soon.
Oct 4: Asphalt overlay and curb repairs continue on St. Bernard Ave and Gentilly Blvd. Crews plan to reach substantial completion by the end of next week.
Sept 23: St. Bernard Avenue (N. Rampart - Sere): Pavement patching in the southbound lane from N. Prieur to N. Johnson is underway. Crews are also placing median ramps near Paris intersection. Gentilly Boulevard (Paris - N. Broad): Paving of the high lanes, in each direction, from Treasure to Laharpe is underway.
Sept 17: Paving continues on St. Bernard Avenue between N. Rampart and Claiborne. Water leak at Gentilly and Fortin has been repaired by Sewerage and Water Board. Crews are now patching the area and installing ADA compliant ramps. Paving on Gentilly (Paris - N. Broad) to begin next week.
Sept 9: Paving of high and low lanes and turn-outs continue this week between Broad and Sere on St. Bernard Avenue. Paving between N. Rampart and Claiborne to follow. Sewerage and Water Board crews to continue repairs to the waterline leak at the Fortin and Gentilly intersection.
Sept 3: Paving and installation of median ramps continue on St. Bernard Avenue from Claiborne to Sere. Sewerage and Water Board crews to repair waterline leak at Fortin Street and Gentilly Boulevard intersection.
Aug 26: Crews are leveling St. Bernard Avenue. Paving to begin Wednesday, August 28 from N. Rampart to Claiborne. Then, proceed from Claiborne to Sere. Median ramp installation continues on Gentilly Blvd.
Aug 16: St. Bernard Ave (N. Rampart - Sere) Pavement patches and curb repairs underway. Asphalt overlaying between N. Rampart and Claiborne to begin by Friday, August 23. Gentilly Blvd (Paris – N. Broad): Pavement patches and curb repairs underway.
Aug 9: St. Bernard Ave (N. Rampart - Sere): Pavement patching in high lanes, stone curb repair and ADA-ramp installation to continue the week of August 12. Gentilly Blvd (Paris - Broad): Pavement patching continues in low lanes, then will switch to high lanes, and ADA-ramp installation to continue the week of August 12.
Aug 5: St. Bernard Avenue (N. Rampart - Sere): Cold milling is complete. ADA-ramp installation continues at Henriette Delille, Roman, Derbigny and Claiborne intersections. Pavement patching resumes in northbound and southbound outside lanes. Gentilly Boulevard (Paris – Broad): Cold milling is complete. ADA-ramp installation continues. Pavement patching resumes in northbound and southbound outside lanes.
Jul 30: St. Bernard Avenue (N. Rampart – Gibson): Cold milling has resumed and projected to complete by Friday, August 2. Gentilly Boulevard (Paris – Broad): Cold milling has resumed and projected to be complete by Friday, August 2. ADA ramp installation continues, proto be complete by Friday, August 9.
Jul 25: Gentilly Boulevard (Paris - Broad): Crews will resume cold milling operations on Wed, July 31 after the SWBNO waterline replacement is complete at the 1600 and 1800 blocks.
Jul 19: Crews are installing inlet protection at the catch basins of St. Bernard and Gentilly. The inlet protection is used for erosion control. Please do not interfere with the inlet protectors; otherwise, construction debris will clog the drains.
Jul 17: Crews are excavating and installing ADA ramps at street corners along low lanes of Gentilly and St. Bernard.
Jul 9: Roadway patching, bus pad, curb repairs, stone curb resetting and ADA ramp installation continue on St. Bernard Ave. Manholes and catch basins are also being adjusted to what will be the final asphalt elevation. Cold milling is tentatively scheduled to resume and be completed next week on Gentilly Blvd; roadway patching and curb repair have begun; ADA ramp installation continues.
Jul 1: St. Bernard Avenue (N. Rampart – Gibson): ADA ramps are being excavated. Concrete pouring starts this week. Crews will pavement patch areas and repair curbs this week. Gentilly Boulevard (Paris – Broad): Cold milling continues. Crews are excavating and preparing roadway patches and curb to be placed next week.
Jun 20: St. Bernard Avenue: Pavement patches are being excavated. Concrete pouring to begin Friday or Monday between Claiborne and Broad in the northbound and southbound lanes. Installation of ADA ramps continue. Gentilly Boulevard: Crews begin saw-cutting, excavating, and forming ADAramps. Concrete pouring projected to start early next week. Cold milling is complete on the northbound roadway andits turnouts. Milling of the southbound lane and its turnouts will begin following the completion of the S&WB’s waterline repairs.
Jun18: Cold milling continues on the northbound median lane on Gentilly Blvd. Crews are also saw cutting and excavating ramps at sidewalk corners.
Jun 13: Cold milling on St. Bernard Avenue from N. Rampart to N. Broad is complete, turnouts and crossovers included. The installation of ADA ramps and milling operations on St. Bernard will continue tomorrow from N. Broad to Desaix. Crews will begin cold milling operations on Gentilly Boulevard from Paris Avenue to N. Broad on Saturday, June 15. * Weather and unforeseen events pending.
Jun 3: St. Bernard Avenue: Cold milling has begun on St. Bernard Avenue between Rampart and Claiborne. One lane in each traveling direction will remain open to traffic. On-street parking will be restricted throughout construction. ADA ramp installation at the sidewalk intersections has also begun.
Jun 1: Construction begins on St. Bernard Avenue
May 9: Neighborhood informational meeting held at Mount Calvary Church of God in Christ, Fellowship Hall to discuss upcoming roadway rehabilitation.
May 2: Neighborhood informational meeting will be held on Thursday, May 9 at 6:00 p.m. at Mount Calvary Church of God in Christ, Fellowship Hall to discuss upcoming roadway rehabilitation.
B1: City Park Ave. and Esplanade Ave.
City Park Avenue (Canal Boulevard – Orleans Avenue)
Esplanade Avenue (Moss Street - N. Claiborne Avenue)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
*Esplanade Avenue from Moss to N. Claiborne will be restriped as one travel lane bicycle lane and parking lane in both directions.
Dec 11: The installation of bike symbols and signage is underway on Esplanade and City Park.
Dec 3: Installation of bike signage has begun. Crews will return to Esplanade and City Park to install bike symbols on Friday, Dec 6 or Monday Dec 9.
Dec 2: Crews will return to City Park and Esplanade this month to install bike symbols and arrows. The installation will occur after the striping of Basin Street between N. Claiborne and Canal is complete.
Aug 27: The city and state are ironing out details for the installation of bike symbols. A supplemental agreement has been established, funding is in place, but must be transferred to the appropriate subgroups. An installation date is yet to be determined. Efforts are being made to expedite the process.
Jul 31: Bike symbols are an enhancement to the Paths to Progress program. Bike symbols were scheduled to be installed by July; however, a supplemental agreement had to take place prior to the installation. As soon as the local government established funding, bike symbols were ordered. The contractor will install the symbols as soon as the order is received.
Jun 28: Permanent striping on City Park & Esplanade is complete. Bike symbols and signage installations to be complete within 2 weeks.
Jun 24: DOTD District Administrator Michael Stack is joined by state and local officials to celebrate completion of the City Park & Esplanade project at the ribbon-cutting ceremony held at Cabrini High School.
Jun 21: Ribbon-Cutting ceremony meeting to be held on Monday, June 24 at 10:30 a.m. at Cabrini High School Alumnae Hall to celebrate the project completion.
Jun 18: Permanent striping continues on City Park and Esplanade. On-street parking will be restricted during striping process.
May 31: Crews reach substantial completion on Esplanade and City Park Avenues. Permanent striping to be complete within 30 days.
May 14: Roadway pavement patching, cold milling and pavement overlaying have been completed on Esplanade and City Park. ADA ramp installation continues. Minor curb repair is underway on City Park.
April 8: City Park Avenue: Paving will begin tomorrow (Tues) starting with the inside lane at I-10 paving towards Orleans and then Orleans back to I-10. Esplanade: Milling operations continue between Moss and Broad.
April 4: City Park Avenue: Contractor will begin paving next Tuesday, April 9. Work will begin at the Canal St end of the project and proceed east towards Orleans Ave. The contractor will turn the paver around and return to Canal St.
This will affect the City Park Ave/Canal St-Canal Blvd intersection twice on that day. There will be times when thru traffic will not be allowed to cross the newly placed asphalt at the Canal St–Canal Blvd intersection. Right turns will be the only movement allowed.
April 3: City Park Avenue: ADA ramp installation still in progress; paving scheduled to begin Friday, April 5. Esplanade: ADA ramp installation still in progress; milling operations in progress from Moss to Broad starting in parking lanes working towards neutral ground.
March 29: Esplanade Avenue Crescent City Classic update: barricades and cones have been pulled back to the curb and both travel lanes opened today for tomorrow's race. On Monday, April 1, the lane closure will be reinstalled to begin construction on Tuesday, April 2.
March 26: City Park Avenue: Contractor to begin March 27 milling of roadway eastbound from the railroad tracks to Orleans Avenue; expected to be completed by March 28. Esplanade: ADA ramp installations and pavement patching continues; outside lanes only.
March 12: City Park Avenue: Cold milling underway. Esplanade: Pavement patching and ADA accessible ramp installation.
March 11: ADA accessible ramp installation begins on Esplanade Avenue.
March 6: Construction begins. One-lane closure in both directions on Esplanade Avenue from Moss to Claiborne for tree trimming operations.
March 5: Groundbreaking ceremony held on Tuesday, March 5 at 2:00 p.m. at Our Lady of Holy Rosary Catholic Church.
Jan 18: Neighborhood informational meeting held on Thursday, Jan. 18 at 6:00 p.m. at Our Lady of Holy Rosary Church to discuss upcoming roadway rehabilitation.
A3: Clearview Parkway
Clearview Parkway (Veterans Memorial Boulevard – Kawanee Avenue)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Nov 14: Paving is complete and temporary striping is in place; permanent striping to follow. Crews began to reopen the travel lanes and remove traffic control devices today, Nov 14.
Nov 5: Paving to begin tomorrow. Crews to start paving at Veterans and move towards Kawanee.
One lane, in each direction, will remain closed to traffic while rolling closures of street intersections start. Only intersections within close proximity to the paver will be restricted at a time. Temporary closures of intersections will last up to 45 mins and then reopen when the new asphalt hardens.
Oct 28: Crews are pavement patching in low lanes, in each direction and cold milling the turn-outs. Paving to follow.
Oct 22: Crews continue to install ADA ramps in high lane, in each direction. Cold milling to begin tomorrow, Oct 23.
Oct 7: Crews continue to install ADA-compliant ramps and begin pavement patching this week. One lane in each traveling direction will remain open throughout construction.
Oct 4: No repairs are scheduled for the weekend due to Tropical Storm Karen.
Sept 23: Repairs officially begin on Clearview Pkwy as crews saw cut and excavate pavement in low lanes.
Sept 19: Crews will begin installing ADA compliant ramps on Monday, Sept 23. One lane in each traveling direction will remain open throughout construction.
Sept 16: Neighborhood information meeting held at John Calving Presbyterian Church to discuss road repairs scheduled to start Sept 23, 2013.
Sept 9: Neighborhood informational meeting to be held on Monday, September 16 at 6:00 p.m. at John Calvin Presbyterian Church, Fellowship Hall, 4201 Transcontinental Drive, Metairie, La to discuss upcoming roadway rehabilitation projected to begin Monday, September 23.
A2: Robert E. Lee Blvd., Franklin Ave., Filmore Ave.
Robert E. Lee Boulevard (Elysian Fields Avenue – Franklin Avenue)
Franklin Avenue (Filmore Avenue – Gentilly Boulevard)
Filmore Avenue (West End Boulevard – Canal Boulevard)
Filmore Avenue (Marconi Drive – Wisner Boulevard)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Sept 24: Permanent striping is underway. All lanes of travel in each direction have opened for the Robert E. Lee, Franklin and Filmore street segments.
Sept 19: Crews have reached substantial completion of this project. The contractor has 30 days to complete permanent striping.
Sept 11: Filmore (West End - Milne): Paving of lanes, median cross overs and turn outs continue. Filmore (Milne - Canal): Permanent striping underway. Only one lane in one direction is open. Filmore (Marconi - Wisner): Permanent striping and bike sign installation underway. Franklin (Gentilly - Filmore): Manhole adjustments and paving underway. Robert E Lee (Elysian Fields - Franklin): Crews are asphalt overlaying the shoulder lane and turnouts.
Sept 4: Filmore (West End - Milne): Paving of all lanes, median cross overs and turn outs are underway. One lane of traffic remains open in both traveling directions. Filmore (Milne - Canal) Only one lane in one direction is open. Alternative lane closures are expected throughout paving to allow the new asphalt to cure.
Filmore (Marconi - Wisner): Permanent striping and bike sign installation are scheduled for next week. Franklin (Gentilly - Filmore): Cold milling and manhole adjustments underway. Asphalt overlaying to follow. One lane in each traveling direction remains open. Robert E Lee (Elysian Fields - Franklin): Paving of EB and WB lanes are underway. Concrete pavement repairs, curb and ADA ramps are complete.
Aug 26: Filmore (Marconi - Wisner): Paving begins this week along with manhole adjustments. Filmore (West End - Canal): Paving to be complete this week. Permanent striping to follow. Franklin (Gentilly - Filmore): ADA-ramp installation along with pavement, curb and bus pad repairs continue this week.
Robert E Lee (Elysian Fields - Franklin): Paving and manhole adjustments underway.
Aug: 13: Filmore(Marconi - Wisner): Crews to place embankment material on the shoulder then proceed with striping. Filmore (West End - Canal): Asphalt overlaying projected to begin Wednesday, August 14.
Franklin (Gentilly - Filmore): ADA-ramp installation along with pavement, curb and bus pad repairs continue this week. Robert E Lee (Elysian fields - Franklin): Low lanes are open to traffic. Crews continue work on pavement patches, curb repairs and ADA-ramp installation.
Aug 5: Filmore Ave (Marconi - Wisner): Both directions of travel open. Final wearing course placed on traveling lanes and bike lanes. Striping to proceed in upcoming weeks. Filmore Ave (West End - Canal): Between West End and Milne, high lane is closed to traffic in both directions. Between Milne andCanal, only eastbound is open. Panel repairs underway.
Franklin Ave (Gentilly - Filmore): Crews continue pavement patching, bus pad repairs, median ADA ramps & curb repair in high lanes. Robert E Lee Blvd (Elysian Fields - Franklin): Crews placing temporary asphalt in eastbound low lanes. Pavement & curb repairs continue in westbound high lanes.
Jul 16: Filmore (Marconi - Wisner): Both directions of travel are open. Crews will soon place embankment material on the shoulder then proceed with striping.
Filmore (West End - Canal): High lanes are open to traffic between West End and Milne. Tomorrow morning, crews to switch traffic to the low lanes. Only the eastbound is open to traffic between Milne and Canal. Crews are working on the right roadway on pavement repairs, ADA ramps & curb.
Franklin (Gentilly - Filmore): Northbound and southbound low lanes are closed. Contractor is working on pavement repairs, bus pad repairs, curb & ADA ramps. Robert E Lee (Elysian Fields - Franklin): Eastbound & westbound low lanes are closed. Crews are working on pavement repairs, ADA ramps & curb.
Jul 11: Filmore Avenue from Marconi to Wisner is now open to traffic in each traveling direction.
Jul 8: Filmore (West End – Canal): ADA ramp installation in process. Panel and curb repair continues. Filmore(Marconi – Wisner): Westbound widening and pavement overlaying in process. Franklin (Filmore – Gentilly): ADA ramp installation in process. Panel and curb repair continues. Robert E. Lee (Elysian Fields – Franklin): ADA ramp installation continues.
Jun 25: Franklin (Gentilly - Filmore): Installation of ADA ramps continue. Pavement repairs begin today and will continue throughout the week. Westbound low lane is closed.
Robert E Lee (Franklin - Elysian Fields): Southbound low lanes are closed as crews prepare for ADA ramp installation and begin pavement repairs. Repairs expected to continue all week. Northbound low lane is closed due to Sewerage & Water Board project.
Filmore (West End - Canal): Canal to Milne westbound end is closed. The 2 way traffic is on the eastbound lanes. Eastbound and westbound low lanes are closed from Milne to West End for ADA ramp installation and pavement repairs. Work is expected to continue all week.
Filmore (Marconi - Wisner): Eastbound lanes closed. Only westbound lanes are open - detour in place. Leveling of eastbound lanes will be completed today, traffic switched to close westbound as cold milling begins. Cold milling, asphalt patching, and bike lane widening to continue this week. Wearing course (both lanes) to be placed when westbound bike lane is completed.
Jun 18: Crews begin saw cutting ADA compliant ramps and panels.
April 2: Schedule adjusted to first accommodate New Orleans Sewerage & Water Board construction on streets in the Paths to Progress program. Construction proposed to begin Summer 2013.
Jan 24: Neighborhood informational meeting held at 6:00 p.m. at Gentilly Baptist Church to discuss upcoming roadway rehabilitation.
A1: Williams Blvd., West Metairie Ave., Roosevelt Blvd.
Williams Boulevard (Airline Drive – 3rd Street)
West Metairie Avenue (Williams Boulevard to Roosevelt Boulevard)
Roosevelt Boulevard (Airline Drive – West Metairie Avenue)
Roosevelt Boulevard (West Metairie Avenue – Veterans Boulevard)
Repairs include resurfacing, pavement patching, repairing curbs, if needed, and installing ADA-compliant accessible ramps. *The scope of work does not include sidewalk or driveway repairs.
Dec 11: Roosevelt Blvd (W. Metairie - Veterans): All lanes are open for travel. Crews have removed traffic control, barricades and cones. Permanent striping will continue with flagmen on-site.
Dec 9: Roosevelt Blvd (W. Metairie – Veterans): All lanes are open between W. Metairie and W. Napoleon. Northbound lanes between W. Napoleon and Veterans are closed to traffic while southbound is open. Permanent striping to proceed when weather permits.
Dec 2: Roosevelt Blvd (W. Metairie – Veterans): Crews continue pavement and curb repairs. Southbound parking lane between W. Metairie and W. Napoleon is closed to traffic. Northbound traffic between W. Napoleon and Veterans is also closed while southbound remains open.
Nov 18: Roosevelt Blvd (W. Metairie – Veterans): Pavement repairs continue in the parking lane between W. Metairie and W. Napoleon and the northbound lanes between W. Napoleon and Veterans. Southbound lanes are open.
Nov 7: Tomorrow, crews to swap traffic on Roosevelt Blvd (between Veterans and W. Napoleon). Traffic will be routed one way southbound.
Oct 28: Roosevelt (W. Metairie - Napoleon): Pavement patching in the traveling lanes of each direction is underway. The parking lanes are open for travel. Roosevelt (Napoleon - Veterans): Southbound lane remains closed and traffic detoured to the next major roadway, Williams Blvd. The northbound lane remains open to traffic.
Oct 21: Today, crews begin panel replacements and curb repairs on Roosevelt Blvd (W. Metairie - Veterans). The following road closures and detour will be in effect. Roosevelt (W. Metairie - Napoleon): High side lane (median side) to close northbound and southbound. Low lanes to remain open. Roosevelt (Napoleon - Veterans): Southbound lane to close and detour. Northbound lane to remain open.
Oct 14: Additional work will be performed on Roosevelt Boulevard between W. Metairie and Veterans starting the week of October 21st or soon after. This work will require periodic lane closures; yet, one lane in each direction will remain open throughout construction. Repairs include curb repair and panel replacements. Work is expected to last 45 calendar days.
Jun 18: Crews reached substantial completion of project on Monday, June 17. Striping continues and will be completed within 30 days.
Jun 3: W. Metairie Ave: Crews begin paving eastbound lane of West Metairie Avenue. One travel lane will remain open at all times. Traffic will switch to the low eastbound lane when the asphalt has cooled. Paving the eastbound lane will continue tomorrow.
May 6: Williams Blvd: ADA ramp installation continues. Pavement overlaying to begin within 2 weeks. W. Metairie Ave: Removing and replacing roadway next to the canal while traffic remains open to the recently rehabilitated lane.
Roosevelt Blvd. (Airline Dr. - W. Metairie Ave): Switching traffic to the recently rehabilitated lane while we remove and replace roadway in the closed lane. Roosevelt Blvd. (W. Metairie Ave. - Veterans Blvd.): ADA ramp installation continues. Adding roadway panels at 21st Street.
April 8: ADA-compliant ramps installation begins on Williams Blvd., W. Metairie Ave and Roosevelt Blvd.
April 2: Neighborhood informational meeting held Tuesday, Apr. 2, 6:00 p.m. at Kenner City Hall Council Chambers to discuss upcoming roadway rehabilitation.
FRENCH QUARTER UPDATES
February 19
Posted “No Parking” signs on Dauphine yesterday for effective date of Wednesday, February 20, 2013. Closures will be rolling and long enough to allow the joint sealant to cure starting at Esplanade working towards Canal.
January 7-February 1
Project-wide: Completing street name tile installation, clean-up efforts, etc.
January 4-7
Project-wide: Completing street name tile installation
Royal: Curb re-exposure in 900 and 1000 block
N. Peters/Decatur: Pedestrian island installation at Conti and Iberville
January 2-3
Project-wide: Completing street name tile installation
Royal: Curb re-exposure in 900 and 1000 block
N. Peters/Decatur: Pedestrian island modifications
December 26-29
Project-wide: Completing street name tile installation
N. Peters/Decatur: Pedestrian island modifications
December 21-22
Project-wide: Completing street name tile installation
Royal and Orleans: Cobblestone crosswalk stone removal and replacement
Royal Street: Sidewalk removal and replacement in 800 and 900 block has been completed
*No work to be done from December 23-25
December 12-19
Toulouse/St. Louis/Dauphine/Decatur/N.Peters: Sidewalk repairs and street name tile installation; Sidewalk and shoulder area adjacent to the sidewalk localized closure.
Royal Street: Sidewalk removal and replacement in *800 and 900 block; curb re-exposure in 900 and 1000 block *The 800 and 900 blocks of Royal Street sidewalks were not removed andreplaced originally due to safety hazards with shallow electrical conduits. Entergy representatives reported the existing conduits in these blocks immediately below the existing concrete sidewalk. Through the use of alternative methods of concrete removal and coordinating closely with Entergy, it has been determined there will be additional sidewalk removal and replacement in the 800 and 900 blocks of Royal Street.
St. Louis/Toulouse/N Peters/Decatur: Crosswalk and corner-zone striping to continue; Rolling closures at intersections. *There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
December 11
The 800 and 900 blocks of Royal Street sidewalks were not removed and replaced due to safety hazards with shallow electrical conduits. Entergy representatives reported the existing conduits in these blocks immediately below the existing concrete sidewalk.
Through the use of alternative methods of concrete removal and coordinating closely with Entergy, it has been determined there will be additional sidewalk removal and replacement in the 800 and 900 blocks of Royal Street.
The contractor will engage the services of a utility locator and Entergy. Once the conduit location is determined, the concrete sidewalk will be removed and replaced and the stone curb reset, where possible.
The areas of sidewalk marked with white arrows will be removed and replaced beginning Wednesday, December 12.
If you have any questions, please call 1-800-574-7193, mail P.O. Box 56845, New Orleans, LA 70156-6845, or email paths2progress@gmail.com.
December 6-11
Royal/Toulouse/St. Louis/Dauphine/Decatur/N.Peters: Sidewalk repairs; Sidewalk and shoulder area adjacent to the sidewalk localized closure
St. Louis/Toulouse/N Peters/Decatur: Crosswalk and corner-zone striping to continue; Rolling closures at intersections. There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
December 4 and 5
Royal/Toulouse/St. Louis/Dauphine: Sidewalk repairs; Sidewalk and shoulder area adjacent to the sidewalk localized closure
St. Louis/Toulouse/N Peters/Decatur: Crosswalk and corner-zone striping to continue; Rolling closures at intersections. There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
November 30
N. Peters/Decatur: Paving operations at intersections for turn-outs; asphalt driveway tie-ins installed project-wide
Royal/Toulouse/St. Louis/Dauphine: Sidewalk repairs; Sidewalk and shoulder area adjacent to the sidewalk localized closure
St. Louis/Toulouse/N Peters/Decatur: Crosswalk and corner-zone striping to continue; Rolling closures at intersections. There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
November 29
Royal/Toulouse/St. Louis/Dauphine: Sidewalk repairs; Sidewalk and shoulder area adjacent to the sidewalk localized closure
St. Louis/Toulouse/N Peters/Decatur: Crosswalk and corner-zone striping to continue; Rolling closures at intersections. There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
November 26
Royal/Toulouse/St. Louis/Dauphine: Sidewalk repairs; Sidewalk and shoulder area adjacent to the sidewalk localized closure
Decatur/N Peters: Paving operations at intersections for turn-outs with rolling closures*
St. Louis/Toulouse/N Peters/Decatur: Crosswalk and corner-zone striping to continue; Rolling closures at intersections. *There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
*Weather permitting
November 24
Possible isolated sidewalk and street name tile replacement
November 21
Royal/Toulouse/St. Louis/Decatur: Sidewalk repairs; Sidewalk and shoulder area adjacent to the sidewalk localized closure
Decatur/N Peters: Paving operations at intersections with rolling closures
Burgundy/Dauphine/Esplanade/Royal: Crosswalk and corner-zone striping to continue; Rolling closures at intersections *There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
There will be no work on Thursday and Friday.
November 20
Royal/Toulouse/St. Louis/Decatur: Sidewalk repairs; Sidewalk and shoulder area adjacent to the sidewalk localized closure
Decatur/N Peters: Continue of paving operations with rolling closures
Burgundy/Dauphine/Esplanade/Royal: Crosswalk and corner-zone striping to continue; Rolling closures at intersections *There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
November 19
Dauphine/Royal: Intermittent closures for sidewalk repairs
Decatur/N Peters: Continue of paving operations with rolling closures
Burgundy/Dauphine: Crosswalk and corner-zone striping to continue; Rolling closures at intersections *There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
November 17
Dauphine/Royal: Intermittent closures for sidewalk repairs
Burgundy/Esplanade: Crosswalk and corner-zone striping to continue; Rolling closures at intersections *There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
November 16
Dauphine/Royal: Intermittent closures for sidewalk repairs
Decatur/N Peters: Continue of paving operations with rolling closures
St. Louis: Rolling closures for clean-up operations
Burgundy/Dauphine: Crosswalk and corner-zone striping to continue; Rolling closures at intersections *There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
November 15
Dauphine/Royal: Intermittent closures for sidewalk repairs
Decatur/N Peters: Start of paving operations at Canal with rolling closures
St. Louis: Rolling closures for clean-up operations
Burgundy/Dauphine: Crosswalk and corner-zone striping to continue; Rolling closures at intersections *There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
November 14
Dauphine/Royal: Intermittent closures for sidewalk repairs
Decatur/N Peters: Rolling closures for manhole adjustments
St. Louis: Rolling closures for paving operations to continue
Burgundy/Dauphine: Crosswalk and corner-zone striping to be begin; Rolling closures at intersections *Note: Scheduled to begin 11/13, but instead will begin 11/14. There will be temporary closures at the intersections while striping is being laid. There will also be temporary closures to the block approaching striping operations.
November 13
Dauphine/Royal: Intermittent closures for sidewalk repairs
Decatur/N Peters: Rolling closures for manhole adjustments
St. Louis: Paving operations to begin
Burgundy/Dauphine: Striping to be begin; Rolling closures at intersections
November 12
Dauphine: Intermittent closures for sidewalk repairs
Royal: Intermittent closures for sidewalk repairs
Decatur/N Peters: Rolling closures for manhole adjustments
Toulouse: Rolling closures for paving turn-outs and crossovers at intersections
St. Louis: Paving operations to begin
November 9
Dauphine: Intermittent closures for sidewalk repairs
Royal: Intermittent closures for sidewalk repairs
St. Louis: Intermittent closures for sidewalk repairs
Decatur/N Peters: Rolling closures for manhole adjustments
Toulouse: Paving operations to continue
November 8
Dauphine: Intermittent closures for sidewalk repairs
Royal: Intermittent closures for sidewalk repairs
St. Louis: Intermittent closures for sidewalk repairs
Decatur/N Peters: Rolling closures for clean-up milling operations
Toulouse: Paving operations to begin starting at N Rampart
November 7
Dauphine: Paving operations for turn-outs and cross overs at intersections; Rolling closures
Royal: Paving operations for turn-outs and cross overs at intersections; Rolling closures
Decatur/N Peters: Milling operations to continue
November 6
Royal Street closed at Barracks by others
St. Peters at Chartres closed by others for renovations at Le Petit Theatre
Conti from Decatur to N. Front, Conti from Chartres to Decatur closures by others to install conduits
November 6
Dauphine: Paving operations to continue; Rolling closures for turn-out and cross over paving; Closures at cross streets when paving operations are at the intersection
Decatur/N. Peters: Rolling closures for milling operations to continue starting at Dumaine working towards Canal
St. Louis: Intermittent closures to excavate and pour concrete for manhole adjustments and pavement patching from Decatur to N Rampart
Toulouse: Intermittent closures to excavate and pour concrete for manhole adjustments and pavement patching from N Rampart to Decatur
November 5
Decatur/N. Peters: Rolling closures for milling operations to begin starting at Canal working towards Dumaine
Dauphine: Paving operations to continue; Rolling closures
St. Louis and Toulouse: Intermittent closures to excavate and pour concrete for manhole adjustments and flagstone sidewalk replacements
November 2
Dauphine: Paving operations to continue; Rolling closures
Toulouse: Intermittent closures to excavate and pour concrete for manhole adjustments and flagstone sidewalk replacements
*St. Louis from Chartres to Royal and St. Louis from Royal to Bourbon (leaving Royal Street intersection open) no access will be allowed Friday, Nov. 2 and Saturday, Nov. 3 for manhole adjustments and pavement patch base repairs. These blocks will reopen on Sunday, Nov. 4.
November 1
Dauphine: Paving operations to begin; Rolling closures
October 31
Closures due to construction activities from 5AM-7PM:
- Royal: Rolling closures for paving operations at intersections
- Dauphine: Rolling closures for concrete placement for manhole adjustments
October 29
Sidewalk removal and replacement
· Sidewalks in poor condition were considered for removal and replacement
· Sidewalks are not removed and replaced under galleries and 12” from building foundations due to structural uncertainties
· Some areas of sidewalk were not removed and replaced due safety concerns with shallow electrical lines
Milling and paving operations
· The project schedule list of streets in order is as follows: Note: Dauphine moved in the schedule for paving to immediately after Royal.
1. Burgundy (Sidewalks, milling and mainline paving overlay completed; turn-out and crossover paving underway)
2. Esplanade (Sidewalks and milling completed; mainline paving overlay complete; turn-out and crossover to follow Burgundy)
3. Royal (Milling complete; stone sidewalk underway; mainline paving overlay underway)
4. Dauphine (Sidewalk underway; milling completed; overlay to follow Royal)
5. Toulouse (Sidewalk underway; milling completed; overlay to follow Dauphine completion)
6. St. Louis (Sidewalk underway; milling completed; overlay to follow Toulouse)
7. Decatur/N Peters (Sidewalk underway; milling and overlay to follow St. Louis)
· Milling machine removes 2” of asphalt on the existing roadway, paving with 2” of new asphalt
· During paving operations, there will be period of time during construction hours (approx. 2-3 hours) that absolutely no vehicular traffic can drive on fresh asphalt as this will cause damage to the new surface
Termite trap procedure
· Paths to Progress has coordinated with the City of New Orleans Mosquito and Termite Control
· In areas of sidewalk that Paths to Progress removes and replaces where a termite trap was located, the contractor will core the sidewalks at the spacing and location per the current standards. These standards are 18” from the property and 10’ spacing.
· The property owner will be notified and need to contact their termite bait service provider for re-installation of bait traps. (Letters have begun distribution.)
Manhole Covers
· Manholes will be adjusted as needed during and following overlay operations. The covers may get covered by asphalt, but will be cleaned and/or replaced as necessary at the end of the project.
Street Light Foundation
· Existing street light post foundations affected by sidewalk construction will remain in place or be reinstalled as necessary
Vibrations
· This is monitored during the milling process and vibrations measured to adhere to federal standards
Street Name Tiles
· Street name tiles will be installed per standard plans. Any installed not meeting these standards will be corrected before the project is complete.
Project clean-up
· The contractor is required to complete a project-wide clean-up
· As this is a working construction site, thank you for your patience with construction materials, equipment and crews in the area
October 26 and 29
Closures for construction activities from 5AM-7PM:
- Royal: Paving operations to begin; Rolling closures starting at Esplanade for leveling and mainline paving
- Burgundy: Rolling closures at intersections for paving turnouts starting at Iberville working towards Esplanade
- Dauphine: Rolling closures for chipping and cleaning starting at Esplanade
For more information about Paths to Progress, please call 1-800-574-7193.
October 25
Closures for construction activities from 5AM-7PM:
- Esplanade: Rolling closures at intersections for turnout and cross over paving operations
- Dauphine: Rolling closures for milling operations from Toulouse to Canal
- Royal: Rolling closures from St. Philip working towards Canal for manhole adjustments; Paving operations to begin Friday, Oct. 26 starting at Esplanade
October 24
Closures for construction activities from 5AM-7PM:
- Royal: Concrete placement for manhole adjustments; Rolling temporary closures from Toulouse towards Canal
- Dauphine: Milling operations from Dumaine to St. Louis
- Esplanade: Paving of turnouts and crossovers; Temporary closures starting at N. Rampart working towards N. Peters
October 23
French Quarter closures from 5AM-7PM for milling/paving operations:
- St. Louis: Rolling closures for clean-up operations
- Dauphine: Milling operations underway from Barracks to St. Ann
- Esplanade: N. Rampart to N. Peters rolling closures for paving operations
- Royal: Rolling closures to complete manhole adjustments
October 22
French Quarter closures from 5AM-7PM for milling/paving operations:
- St. Louis: Rolling closures to complete milling operations
- Dauphine: Milling operations to begin starting at Esplanade once St. Louis milling is complete
- Esplanade: N. Rampart to N. Peters rolling closures for paving operations beginning on the lake bound side
- Toulouse: N. Rampart to Decatur rolling closure for cleanup operations
- Royal: Rolling closures to complete manhole adjustments
*No work will be done Saturday, October 20
October 19
French Quarter closures from 5AM-7PM for milling/paving operations:
- St. Louis: Decatur to N. Rampart rolling closures for milling operations
- Esplanade: N. Rampart to N. Peters rolling closures for paving operations beginning on the river bound side
- Toulouse: N. Rampart to Decatur rolling closure for cleanup operations
October 18
French Quarter closures from 5AM-7PM for milling/paving operations:
- Toulouse: Milling operations are complete from N. Rampart to Royal; Rolling closures from Royal to Decatur on Oct. 18
- St. Louis: Milling operations to begin Oct. 19 starting at Decatur
- Esplanade: Rolling closures for paving operations both N. Rampart and N. Peters bound
No other closures in place.
October 17-18
Royal: Rolling closure for clean-up operations
Toulouse: Start of milling operations at N. Rampart; Rolling closures
Esplanade: Start of paving operations at N. Rampart; Rolling closures
October 15-16
Rolling closure on Royal for milling operations.
Rolling closure on Burgundy for paving operations.
Milling/Paving Operations
Milling operations are complete on Esplanade
Milling operations will continue on Royal
Paving has begun on Burgundy
October 12 Closures from 5AM-7PM
- Burgundy rolling closure for paving operations
- Royal rolling closure for milling operations
- Esplanade rolling closures for clean-up operations
- Dauphine from St. Peter to Bienville: No Parking and daytime closure
- Toulouse from N. Rampart to Bourbon closure: No Parking signs have been posted, effective Friday 10/12/12
Milling/Paving Operations
Milling operations on Esplanade to be complete by end of the day on Tuesday, October 9
Milling operations will begin on Royal on Wednesday, October 10
Paving is scheduled to begin on Burgundy on Thursday, October 11
October 10
Closures from 5AM-7PM
- Burgundy rolling temporary closures for roadway cleanup
- Esplanade closures:
Lakebound: No parking signs from N. Peters to N. Rampart
Riverbound: Rolling closures for clean-up and concrete placement for manhole adjustments
- Dauphine from St. Peter to Bienville: No Parking and daytime closure
- Royal rolling closure for milling operations
October 5-8
Roadway closures from 5AM-7PM for sidewalk and milling operations:
- Burgundy rolling closure for milling clean-up operations
- Esplanade No Parking from N. Rampart to N. Peters for milling operations
- Dauphine closure from St. Peter to Bienville
- Royal closure from St. Peter to Bienville
- St. Louis closure from Decatur to Dauphine
- N. Peters has no closure
October 3
Milling operations on Burgundy are complete.
Esplanade from N. Rampart to Royal will begin milling operations tomorrow, Oct 4.
October 3
Additional roadway closure from 5AM-7PM for sidewalk repairs on St. Louis from Decatur to Dauphine.
Milling operations have progressed on Burgundy and are currently from Dumaine to Esplanade.
No closure on Toulouse.
Closures from 5AM-7PM for sidewalk/roadway repairs are now:
- Burgundy rolling closure from Dumaine to Esplanade for milling operations
- Dauphine closure from St. Peter to Bienville
- N. Peters closure lakeside from St. Louis to Iberville
- Royal closure from St. Peter to Bienville
- Esplanade parking lane closure both directions between N. Rampart and Bourbon
- St. Louis closure from Decatur to Dauphine
October 2-3, 2012
Road/lane closures during construction hours of 5AM-7PM due to repairs:
- Burgundy rolling closure from St. Louis to Dumaine for milling operations; tomorrow Burgundy rolling closure from Dumaine to Esplanade
- Dauphine closure from St. Peter to Bienville
- N. Peters closure lakeside from St. Louis to Iberville
- Royal closure from St. Peter to Bienville
- Esplanade parking lane closure both directions between N. Rampart and Bourbon
- Toulouse closure from Decatur to Bourbon
October 1
Road/lane closures during construction hours of 5AM-7PM due to repairs:
- Burgundy rolling temporary closures for milling operations
- N. Peters closure lakeside from St. Louis to Iberville
- Royal closure from St. Peter to Bienville
- Dauphine no closure in place; possible rolling temporary closures for clean-up crews
- Esplanade parking lane closure both directions between N. Rampart and Bourbon
- Toulouse closure from Decatur to Bourbon
September 28
Milling and paving operations
- Milling and paving operations will begin Monday, October 1
- The milling schedule list of streets in order is as follows: Burgundy, Esplanade, Royal, Toulouse, St Louis, Decatur/N Peters, Dauphine
- Milling machine removes 2” of asphalt on the existing roadway, paving with 2” of new asphalt
- During paving operations, there will be period of time during construction hours (approx. 2-3 hours) that absolutely no vehicular traffic can drive on fresh asphalt
Termite trap procedure
- Paths to Progress has coordinated with the City of New Orleans Mosquito and Termite Control
- Areas of sidewalk that Paths to Progress removes and replaces where a termite trap was located, the contractor will core the sidewalks at the spacing and location per the current standards
- The property owner will be notified and need to contact their termite bait service provider for re-installation of bait traps
ADA compliant ramps
- In order for newly installed ADA ramps to be used during construction, a temporary asphalt patch must be installed for accessibility and compliance, if needed
- When milling and paving operations begin, the temporary asphalt patch will be removed and replaced with the permanent asphalt surface at the correct elevation
Project clean-up
- The contractor is required to complete a project-wide clean-up
- As this is a working construction site, thank you for your patience with construction materials, equipment and crews in the area
September 25
A message from Film New Orleans:
“On Thursday, September 27th, from approximately 6:00 am – 11:59 pm, we will be “on location”–– filming scenes for an upcoming feature length film. Our location is at the corner of Royal Street and St. Ann, located in the French Quarter. There will be intermittent traffic control between the hours of 6pm and 10pm during the filming on Royal Streetbetween Dumaine and Orleans, and St. Ann between Bourbon and Chartres. Times of filming are approximately 6:00 am to 12:00 midnight. Please be aware of the “No Parking” signs posted.
-600-700 blocks of St. Ann -700-800 blocks of Royal St.*
-800 Block of Chartres St. -600 block of Dumaine St.
-700 block of Orleans St. -700 block of Bourbon St.
Our company understands that this is an inconvenience. Especially with the “Paths to Progress” redevelopment of the French Quarter streets. We did our best, to only take non-resident parking; i.e. loading zones & parking meters. It is gratefully appreciated that we are allowed to film in your beautiful city, and are exceedingly thankful for your hospitality. Please feel free to contact us with any questions or concerns.
This filming is being done with the knowledge and cooperation of the Mayor's Office of Cultural Economy / Film New Orleans, and the New Orleans Police Department. For more information, contact Katie Williams at Film New Orleans (504-658-0923 / www.filmneworleans.org).”
*Paths to Progress project limits
September 24
Road/lane closures during construction hours of 5AM-7PM due to pavement patching and sidewalk repairs:
- N. Peters closure lakeside from St. Louis to Iberville
- Royal has no closure currently in place
- Burgundy moving temporary closures to address additional sidewalk items
- Dauphine has no closure currently in place
- Esplanade parking lane both directions between N. Rampart and Bourbon
September 20
Due to shallow electrical lines, various sidewalk areas of Burgundy were originally not scheduled to be removed for safety precautions. Due to cooperation and coordination with Entergy, we were able to determine many of them can be removed and replaced in a safe manner.
Starting today, Burgundy beginning at Canal St., will begin the additional sidewalk removal and replacement. The roadway will not be closed, but No Parking signs in the area will be posted. There may be intermittent closures for brief periods of time while the larger construction equipment is in the area.
Thank you for your patience during our progress.
September 19
Dauphine lane closure shifted two blocks towards Canal. Closure is now from Gov. Nicholls to St. Ann.
September 18
The current road closure for sidewalk repair remains on Royal from St. Ann to St. Louis.
Royal between St. Philip and Dumaine is closed for the removal and replacement of a bus pad. The work should begin today, weather permitting, and be complete by Friday.
September 17
Road/lane closures during construction hours of 5AM-7PM due to pavement patching and sidewalk repairs:
• Burgundy from St. Philip to Esplanade closure.
• Dauphine from Esplanade to St. Philip closure.
• Royal from St. Ann to St. Louis closure.
• N. Peters from St. Louis to Canal, southbound lane closure.
• Esplanade N. Rampart bound: travel lane closure from Royal to N Rampart. Parking lane is now a travel lane.
• Esplanade N. Peters bound: travel lane closure from N Rampart to Royal. Parking lane is now a travel lane.
September 12
Today, the following traffic control/lane closures on Burgundy:
1. Gov. Nicholls to Esplanade
2. Iberville to Conti
All other cross streets on Burgundy should be open to through traffic.
September 11
The road closure/detour at Bourbon and Esplanade has been removed as well as on Burgundy/Ursuline.
September 10
Road/lane closures during construction hours of 5AM-7PM due to pavement patching and sidewalk repairs:
• Burgundy from Dumaine to Barracks closure.
• Dauphine from Esplanade to St. Philip closure.
• Royal from St. Ann to St. Louis closure.
• Decatur from St. Louis to Dumaine, riverside lane closure today.
o Decatur from Dumaine to St. Louis, southbound lane closure beginning tomorrow.
• Esplanade N. Rampart bound: travel lane closure from Royal to N Rampart. Parking lane is now a travel lane.
• Esplanade N. Peters bound: travel lane closure from N Rampart to Royal. Parking lane is now a travel lane.
*Esplanade/Bourbon St intersection, from Barracks to Esplanade is currently closed due to a roadway patch on Esplanade Ave. There may be periodic travel lane closures due to the movement of construction equipment. A flag man is on-site to direct traffic.
September 8
As of today, closure on Dauphine from Esplanade to St. Philip.
September 7
The closure on Decatur has shifted up two blocks. The closure on Decatur is now from St. Peter to Dumaine. All other closures remain.
September 6
Due to pavement patching, the Ursuline intersection at Burgundy will require a temporary detour on Ursuline at Dauphine to Dumaine.
September 5
Road/lane closures during construction hours of 5AM-7PM due to pavement patching and sidewalk repairs:
- As of this morning, Burgundy from Toulouse to Dumaine is open. Today, Burgundy is closed from Dumaine to Barracks.
- Royal from St. Ann to St. Louis closure.
- Decatur from St. Louis to Dumaine, riverside lane closure.
- Esplanade N. Rampart bound: parking lane closure from Royal to N Rampart.
- Esplanade N. Peters bound: parking lane closure from N Rampart to Royal.
*Esplanade/Bourbon St intersection, from Barracks to Esplanade is currently closed due to a roadway patch on Esplanade Ave. There may be periodic travel lane closures due to the movement of construction equipment. A flag man is on-site to direct traffic.
September 4
Road/lane closures, during construction hours of 5AM-7PM, due to repairs:
• Burgundy from Toulouse to Dumaine closure.
• Royal from St. Ann to St. Louis closure.
• N. Peters from St. Louis to Dumaine, riverside lane closure.
• Esplanade N. Rampart bound: parking lane closure from Royal to N. Rampart.
• Esplanade N. Peters bound: parking lane closure from Royal to N. Rampart.
• Dauphine from Esplanade to St. Philip: No Parking.
For more information, please call 1-800-574-7193.
August 27
All P2P projects will be shut down and work zones made safe by the contractor. Work is expected to resume Tuesday, Sept 4.
Please be safe.
August 24-26
Road/lane closures, during construction hours of 5AM-7PM, due to repairs:
- Burgundy from St. Louis to St. Ann closure.
- Royal from Gov. Nicholls to St. Philip.
- N. Peters from Canal to St. Louis, one lane closure.
- Esplanade N. Rampart bound: parking lane closure from Royal to N. Rampart.
- Esplanade N. Peters bound: parking lane closure from N. Peters to Royal St.
August 22
Road/lane closures, during construction hours of 5AM-7PM, due to repairs:
Burgundy from St. Louis to St. Ann closure.
Royal from Gov. Nicholls to St. Ann closure, set for 8/23. (Currently from Gov. Nicholls to St. Philip.)
N. Peters from Canal to St. Louis, one lane closure.
Esplanade N. Rampart bound: parking lane closure from Royal to N. Rampart
Esplanade N. Peters bound: parking lane closure from N. Peters to Royal St.
August 21
Effective first thing Thursday morning 08/23/12, the road closure on Royal St. will shift up two blocks.
Road closure on Royal St., starting Thursday, will be from Gov. Nicholls to St. Ann.
Thank you for your patience during this progress.
August 20-24
Road/lane closures, during construction hours of 5AM-7PM, due to repairs:
• Burgundy from St. Louis to St. Ann closure.
• Royal from Esplanade to St. Phillip closure.
• N. Peters from Canal to St. Louis, one lane closure.
• Esplanade from N. Peters to Royal, one lane closed both directions.
August 18-19
Closures for Saturday, August 18 and Sunday, August 19. Road/lane closures, during construction hours of 5AM-7PM, due to repairs:
• Burgundy from St. Louis to St. Ann closure.
• Royal from Esplanade to St. Phillip closure.
• N. Peters from Canal to St. Louis, one lane closure.
• Esplanade from N. Peters to Royal, one lane closed both directions.
Thank you for your patience.
August 14-23: Esplanade Avenue
Due to pavement patching repairs in the travel lane with open excavations, Esplanade Avenue from N. Peters to Royal, N. Rampart bound side, will require No Parking at any time from August 14-23.
August 14
Esplanade Ave. Traffic Control Update: The N. Rampart bound traffic control has changed. Closure remains N. Peters to Royal, but travel lane is now closed and traffic is traveling in the parking lane.
Thank you for your patience during our progress. For any questions, please call 1-800-574-7193.
August 13-17
Road/lane closures, during construction hours of 5AM-7PM, due to repairs:
• Burgundy from Iberville to Toulouse closure.
• Royal from Esplanade to St. Phillip closure.
• N. Peters from Canal to St. Louis, one lane closure.
For Monday, August 13: Effective this morning, N. Peters from Iberville to Conti will be a one lane two way road. Posted at both Iberville and Conti will be one flagmen and one NOPD Detail officer assisting with traffic flow.
• Esplanade from N. Peters to Royal, both parking lanes will be closed
August 10-12
Schedule for Friday, 8/10:
Road/lane closures, during construction hours of 5AM-7PM, due to repairs:
• Burgundy from Iberville to Toulouse closure.
• Royal from Esplanade to St. Phillip closure.
• N. Peters from Canal to St. Louis, one lane closure.
• Esplanade from N. Peters to Royal parking lane will be closed, N. Rampart bound side.
Schedule for Saturday, 8/11:
Road/lane closures, during construction hours of 5AM-7PM, due to repairs:
• Burgundy from Iberville to Toulouse closure.
• N. Peters from Canal to St. Louis, one lane closure.
• Esplanade from N. Peters to Royal parking lane will be closed, N. Rampart bound side.
No closure on Royal Street.
Schedule for Sunday, 8/12:
Road/lane closures, during construction hours of 5AM-7PM, due to repairs:
• Burgundy from Iberville to Toulouse closure.
• Royal from Esplanade to St. Phillip closure.
• N. Peters from Canal to St. Louis, one lane closure.
• Esplanade from N. Peters to Royal parking lane will be closed, N. Rampart bound side.
August 6
Road/lane closures this week, during construction hours of 5AM-7PM, due to repairs:
- Burgundy from Iberville to Toulouse closure.
- Royal from Esplanade to St. Phillip closure.
- N. Peters from Canal to St. Louis, one lane closure.
- Esplanade from N. Peters to Royal parking lane will be closed, N. Rampart bound side.
If you have any questions, please contact 1-800-574-7193.
August 4
Closures remain on Burgundy, Royal and N. Peters today with the exception of no construction closures/repairs on Esplanade Avenue due to Satchmo SummerFest.
July 30
Closures continue this week, during construction hours of 5AM-7PM, due to sidewalk repairs:
- Burgundy from Canal to St. Louis
- Esplanade parking lane closure from Royal to N. Peters both N. Rampart bound and N.Peters bound
- Royal from Esplanade to St. Phillip
- N Peters riverside right lane from Canal to St. Louis
July 25
Closures throughout the rest of the week, during construction hours of 5AM-7PM, due to sidewalk repairs:
- Burgundy from Canal to St. Louis
- Esplanade parking lane closure from Royal to N. Peters both Rampart bound andN Peters bound
- Royal from Esplanade to St. Phillip
- N Peters riverside right lane from Canal to St. Louis
July 23
Road/lane closures due to sidewalk repairs are as follows:
- Burgundy from Canal to St. Louis
- Esplanade parking lane closure from Royal to N. Peters both N. Rampart bound and N. Peters bound
- Royal from Esplanade to St. Phillip
Dates posted on "No Parking" signs date July 23 - August 15.
July 19
Closure continues on Burgundy from Canal to St. Louis for sidewalk repairs.
Parking lane is closed on Esplanade from N. Peters to Royal for sidewalk repairs. The travel lane remains open.
July 17
Sidewalk work will begin tomorrow for Esplanade Ave. Road closure will begin tomorrow, July 18, on Esplanade Ave. from N. Peters to Royal St. towards N. Rampart during construction hours of 5AM-7PM.
Road closure will continue on Burgundy from Canal to St. Louis during construction hours of 5AM-7PM.